BLD02-02897
| FIRE-Sprinkler Rough-in | 1/31/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | A | PASS |
|
|
RON ; Phone #: ###-#### Fire sprinklers finaled 2/3/2003 10:09:26 AM
|
FIR03-00001
| INSP-Final Inspection | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | A | PASS |
|
|
|
FIR02-00406
| INSP-Final Inspection | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | FAIL |
|
|
After a on site inspection and conversing with Bill Alexander the items stored under the new canopy appear to exceed the classifications the sprinkler system was designed to. The contractor will need to resubmitt information to verify the system is per code. A storage rack has been installed and will require a racking permit before use. 2/3/2003 2:43:44 PM
|
BLD02-02908
| FIRE-Final Inspection | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | PASS |
|
|
fire life safety finaled 2/3/2003 2:37:55 PM
|
FIR02-00311
| INSP-Sprinkler Rough-in | 2/3/2003 | 2/3/2003 | 2/3/2003 12:00:00 AM | P | PART |
|
|
###-#### The main lobby area sprinkler piping can be covered. The main sprinkler piping as it penatrates the block wall in two locations will need to be provided with adequate clearance. Hangers will need to be added at two locations on the existing main 2/3/2003 3:13:40 PM
|