Inspections for the day of: Tuesday, February 3, 2009.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-02487 FIRE-Final Inspection2/3/20092/3/20092/3/2009 5:00:31 PMPFAIL
This inspection was for the first and second floor restrooms. Sprinkler modifications are required due to existing sprinkler heads being located too far from the ceiling and possibly obstructed by duct work and soffits. One sprinkler upright has been painted.. Life safety will be ok in the first and second floor restrooms once a sprinkler permit is issued, inspected and passed.
BLD08-02510 FIRE-Final Inspection2/3/20092/3/20092/3/2009 4:58:17 PMPFAIL
Sprinkler modifications are required due to overspaced pendant heads. Life safety will be ok to pass once a sprinkler permit is issued, inspected and passed.
FIR08-00616 INSP-Sprinkler Rough-in/Hydro2/3/20092/3/20092/3/2009 3:15:36 PMPPART
See the city approved resubmitted plans for the locations where the sprinkler piping can be covered. I requested a set of as-builts showing the actual piping arrangement on the north end of the remodeling work.
FIR08-00757 INSP-Final Inspection2/2/20092/3/20092/3/2009 3:13:51 PMAFAIL
Provide print out of todays signal report, test the duct smoke detectors, provide verification of review comment #20, provide verification of sprinkler coverage at the top of the elevator shaft, provide automatic disconnect and monitoring of the 120 volt power as per review note #6, provide firemans hat functions, recall and shunt trip functions as per 6.16.3, provide as builts showing the additional devices, relocate the smoke and heat detectors to the deck, repair the PIV tamper switch.
FIR08-00341 INSP-Final Inspection2/3/20092/3/20092/3/2009 2:39:21 PMPPASS
Permit finaled. A tree was removed from infront of the strobe in the employee breakroom.