FIR13-00640
| INSP-Final Inspection | 2/3/2014 | 2/3/2014 | 2/3/2014 5:07:36 PM | P | PASS |
|
|
After hours testing and inspection completed and passed per C. Hanson.
|
FIR13-00504
| INSP-Final Inspection | 2/3/2014 | 2/3/2014 | 2/3/2014 5:06:21 PM | P | PASS |
|
|
C/N items verified. Final walkthrough passed. Fire sprinkler permit finaled.
|
FIR13-00524
| INSP-Sprinkler Rough-in | 2/3/2014 | 2/3/2014 | 2/3/2014 5:05:25 PM | P | FAIL |
|
|
Approved plans indicate a max. spacing of 16x16- Noted five locations overspaced at 9' from adjacent walls. Also need to verify materials in contact with CPVC piping are compatible per the mfg. listing such as fire caulk, duct mastic, and cables.
|
BLD12-01001
| FIRE-Conference | 2/3/2014 | 2/3/2014 | 2/3/2014 2:50:17 PM | P | DONE |
|
|
On site conference regarding project related fire alarm and sprinkler work, fire code review note items, project schedule, smoke alarm locations, etc.
|
BLD13-03604
| FIRE-Final Inspection | 1/31/2014 | 2/3/2014 | 2/3/2014 2:46:56 PM | A | NR |
|
|
Need plan review of revised floorplan prior to field inspection.
|
BLD13-03205
| FIRE-Final Inspection | 2/3/2014 | 2/3/2014 | 2/3/2014 2:44:29 PM | P | PASS |
|
|
Fire life safety final approved.
|
FIR12-00639
| INSP-Sprinkler Rough-in/Hydro | 2/3/2014 | 2/3/2014 | 2/3/2014 1:09:16 PM | A | PART |
|
|
OH hydrostatic test of the wet system completed and passed.
|
FIR12-00639
| INSP-Sprinkler Rough-in/Hydro | 2/3/2014 | 2/3/2014 | 2/3/2014 1:07:06 PM | A | PART |
|
|
OH hydrostatic test of the new dry system passed.
|
BLD13-02547
| FIRE-Final Inspection | 1/31/2014 | 2/3/2014 | 2/3/2014 12:00:07 PM | A | PASS |
|
|
"Wave four" completed. Final walkthrough passed. Fire life safety finaled.
|
FIR13-00585
| INSP-Final Inspection | 1/30/2014 | 2/3/2014 | 2/3/2014 11:57:05 AM | A | PASS |
|
|
Previous correction items completed. Functional testing passed. Fire alarm permit finaled.
|