Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE15-00257 Temporary Service2/3/20152/3/20152/3/2015 3:57:56 PMPPASS
Temp pole inspection. Contact is Jay Sprik. Phone #: ###-#### Inspection requested via web by Richard Montgomery t/s u/g n ok
ELE12-01006 Final2/3/20152/3/20152/3/2015 3:31:41 PMPPASS
I''m going to be there at 2, I need about an hour if you can come after 3 that would work. Phone #: ###-#### Inspection requested via web by Neal Rumsey corrections made final ok
ELE14-03242 Final2/3/20152/3/20152/3/2015 2:25:32 PMPPASS
Phone #: ###-#### Inspection requested via web by Chris Chesnut final ok
ELE15-00212 Electrical Rough-In2/2/20152/3/20152/3/2015 1:51:50 PMPPART
Phone #: ###-#### Inspection requested via web by Neal Rumsey partial r/i ok still need r/i on hr's and pop out
ELE11-00142 ELE-Aging Inspection2/3/20152/3/20152/3/2015 1:21:14 PM DONE
too busy
ELE13-00581 ELE-Aging Inspection2/3/20152/3/20152/3/2015 1:20:49 PM DONE
too busy
ELE10-02808 ELE-Aging Inspection2/3/20152/3/20152/3/2015 1:20:23 PM DONE
too busy
GCE14-00212 GCE-Final2/3/20152/3/20152/3/2015 1:19:19 PMPPASS
###-#### corrections made final ok
ELE14-03316 Electrical Rough-In2/2/20152/3/20152/3/2015 12:57:21 PMPPASS
Contact Tom Hartung for underground rough in. Phone #: ###-#### Inspection requested via web by Tom Betty u.ground to electric rm. 125 6-3" conduits and 1-2". Also continuation of 3" for ESSE to col. line GD ok to cover.
ELE15-00089 Conference2/2/20152/3/20152/3/2015 11:24:27 AMADONE
Call prior to going Phone #: 2083520355 >> Inspection requested via mobile web by Dan Monzo discuss loadcenter changeout in "mechanical closet"
ELE15-00234 Electrical Rough-In2/2/20152/3/20152/3/2015 10:44:09 AMAPASS
Call for access code by front door. Phone #: ###-#### Inspection requested via web by David McClellan r/i ok
ELE15-00267 Final2/2/20152/3/20152/3/2015 9:57:16 AMAPASS
Contact: Josh Mangum Phone #: ###-#### Inspection requested via web by Deb Gooden final ok
ELE15-00267 Electrical Rough-In2/3/20152/3/20152/3/2015 9:48:42 AMPPASS
Contact: Josh Mangum Phone #: ###-#### Inspection requested via web by Deb Gooden r/i ok addition to cooler
ELE15-00196 Electrical Rough-In2/2/20152/3/20152/3/2015 9:14:28 AMAPASS
Rod-wall rough in Phone #: ###-#### r/i walls ok
ELE14-02710 Permanent Service2/2/20152/3/20152/3/2015 8:43:42 AMAPASS
Phone #: ###-#### Inspection requested via web by Thomas Jenkins p/s u/g n ok verify ground conductor to bldg. steel and water pipe and plastic bushings inside transformer upon return. Also picture of grounding electrode to concrete footing connection.
ELE14-02710 Electrical Rough-In2/2/20152/3/20152/3/2015 8:40:15 AMAPASS
Rough for change order work. Phone #: ###-#### Inspection requested via web by Thomas Jenkins r/i main bldg. walls ok r/i underground ok inside wash bay bldg.