FIR14-00531
| INSP-Sprinkler Rough-in | 2/2/2015 | 2/3/2015 | 2/4/2015 7:44:52 AM | P | PART |
|
|
Completed rough-in inspection of the 3rd and 4th floors tower 2 living units with the exception of NE end and corner rooms not yet piped. DSW heads at some units not yet installed, need to provide coverage at the riser room chases per plan, noted missing coverage at bedroom in unit 322. Rough-in inspections to be done prior to ceiling insulation, discussed distances to be maintained from light fixtures, ceiling fans, and heat sources per NFPA guidelines.
|
FIR14-00801
| INSP-Sprinkler Rough-in | 2/3/2015 | 2/3/2015 | 2/3/2015 3:34:06 PM | P | PART |
|
|
Verified stamped plans on site, completed overhead rough-in inspection. * NOTE: Need to verify tenting insulation prior to cover. No record to date of an UG fire supply line inspection prior to bury.
|
FIR14-00726
| INSP-Final Inspection | 2/3/2015 | 2/3/2015 | 2/3/2015 2:53:32 PM | P | PASS |
|
|
Scope of fire alarm work completed and passed functional testing. Permit finaled.
|
FIR14-00903
| INSP-Final Inspection | 2/2/2015 | 2/3/2015 | 2/3/2015 2:52:34 PM | A | FAIL |
|
|
Netcon rating of 6 at the time of inspection.
|
FIR14-00392
| INSP-Final Inspection | 2/3/2015 | 2/3/2015 | 2/3/2015 1:38:25 PM | A | PASS |
|
|
Remainder of fire alarm work tested satisfactory. Permit finaled.
|
FIR14-00683
| INSP-Sprinkler Rough-in | 2/3/2015 | 2/3/2015 | 2/3/2015 11:53:57 AM | A | PART |
|
|
Completed rough-in for the dry system building J. Items noted include; replace one CC2 sprinkler with the correct type indicated per plan, remove temp vapor barrier obstructing upright coverage above entry vestibule, two ssu exceed min separation at removed draft stop, missing coverage at one overbuild, provide verification plumbing chases meet non-combustible criteria or install sprinkler protection- ref. to plan annotations.
|
FIR14-00900
| INSP-Sprinkler Rough-in | 2/2/2015 | 2/3/2015 | 2/3/2015 9:49:58 AM | A | PART |
|
|
Verified previous correction notice items. Rough-in passed
|