Inspections for the day of: Tuesday, February 3, 2015.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-00115 FIRE-Final Inspection2/3/20152/3/20152/3/2015 1:57:23 PMPPASS
life safety passed
FIR15-00050 INSP-Final Inspection2/3/20152/3/20152/3/2015 1:51:36 PMPPASS
Permit finaled
FIR14-00517 INSP-Final Inspection2/2/20152/3/20152/3/2015 1:42:32 PMAFAIL
The FACP, fire sprinkler devices, batteries, smoke detector, pull station and several duct smoke detectors tested ok today. Will need to finish testing of the remaining duct smoke detectors prior to a final. Will also need document box, map and knox box.
FIR14-00878 INSP-Final Inspection2/3/20152/3/20152/3/2015 11:58:43 AMPFAIL
Provide additional strobe in Admin area due to wall changes and provide as-builts/test.
NAF15-00003 INSP-Sprinkler Rough-in2/2/20152/3/20152/3/2015 10:59:07 AMPPASS
Rough-in passed. Piping ok to cover. I noted the annual inspection will be required prior to a final sign off.
FIR14-00818 INSP-Sprinkler Rough-in2/2/20152/3/20152/3/2015 10:58:16 AMAPASS
Piping above both restrooms and below both stair ways is ok to cover as marked on the city approved plans.