BLD15-00115
| FIRE-Final Inspection | 2/3/2015 | 2/3/2015 | 2/3/2015 1:57:23 PM | P | PASS |
|
|
life safety passed
|
FIR15-00050
| INSP-Final Inspection | 2/3/2015 | 2/3/2015 | 2/3/2015 1:51:36 PM | P | PASS |
|
|
Permit finaled
|
FIR14-00517
| INSP-Final Inspection | 2/2/2015 | 2/3/2015 | 2/3/2015 1:42:32 PM | A | FAIL |
|
|
The FACP, fire sprinkler devices, batteries, smoke detector, pull station and several duct smoke detectors tested ok today. Will need to finish testing of the remaining duct smoke detectors prior to a final. Will also need document box, map and knox box.
|
FIR14-00878
| INSP-Final Inspection | 2/3/2015 | 2/3/2015 | 2/3/2015 11:58:43 AM | P | FAIL |
|
|
Provide additional strobe in Admin area due to wall changes and provide as-builts/test.
|
NAF15-00003
| INSP-Sprinkler Rough-in | 2/2/2015 | 2/3/2015 | 2/3/2015 10:59:07 AM | P | PASS |
|
|
Rough-in passed. Piping ok to cover. I noted the annual inspection will be required prior to a final sign off.
|
FIR14-00818
| INSP-Sprinkler Rough-in | 2/2/2015 | 2/3/2015 | 2/3/2015 10:58:16 AM | A | PASS |
|
|
Piping above both restrooms and below both stair ways is ok to cover as marked on the city approved plans.
|