ELE12-02755
| ELE-Aging Inspection | 2/3/2016 | 2/3/2016 | 2/8/2016 3:31:07 PM | | DONE |
|
|
left message for Clarence to call for final insp
|
ELE15-04108
| Electrical Rough-In | 2/3/2016 | 2/3/2016 | 2/3/2016 1:46:26 PM | P | PASS |
|
|
Ceiling for cover Phone #: ###-#### Inspection requested via web by kendall bender r/i t grid ceilings ok
|
ELE15-00495
| Conference | 2/3/2016 | 2/3/2016 | 2/3/2016 12:57:19 PM | P | DONE |
|
|
Would like approval for the Draka Lifeline 2hr rated fire cable assybly being used for the firepump. Contact Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves after reviewing product info for fire pump conductors "Draka Lifeline 2 hour fire resistive cable" this product is acceptable for use on this project to feed fire pump. However we are still waiting for confirmation to install overcurrent protection with additional disconnect ahead of fire pump controller disconnect as previously discussed. Asked Toby to hold off on that installation until "fire planning dept. and the NFPA 20" will allow this application.
|
ELE16-00223
| Electrical Rough-In | 2/3/2016 | 2/3/2016 | 2/3/2016 12:43:12 PM | A | PASS |
|
|
Brian Phone #: ###-####-as late as possible this morning-3rd floor atrium r/i 2 walls ok
|
ELE15-03901
| Electrical Rough-In | 2/2/2016 | 2/3/2016 | 2/3/2016 10:27:13 AM | A | PASS |
|
|
Rough in inspection for hard lid area on 5th floor in Clearwater building. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 5th floor hard lid ceilings in bathroom and showers
|
ELE16-00192
| Final | 2/2/2016 | 2/3/2016 | 2/3/2016 9:57:35 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by William Andrews Boise city electrical code#4-05-32 no violation shall be retained, NEC 210.8(B)(5)- in other than dwellings, receptacles within 6 foot of sink shall be GFCI protected.
|
ELE16-00016
| Electrical Rough-In | 2/2/2016 | 2/3/2016 | 2/3/2016 9:32:57 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kendra Lanham r/i garage ok
|
ELE16-00185
| Conference | 2/2/2016 | 2/3/2016 | 2/3/2016 8:55:46 AM | A | DONE |
|
|
Ben Phone #: ###-#### discuss hazardous location requirements for hangers. OK to run rigid metal conduit in areas of footings already poured to transition into office area (unclassified area). Meet article 513 in NEC everywhere else
|