BLD98-02031
| INSP - Framing/Rough-in | 2/3/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | A | CANC |
|
|
02/04/99 407 - trans to 340.
|
BLD98-03069
| INSP - Foundation | 2/3/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | A | PASS |
|
|
02/04/99 407 - footings ok 3 shear wall required at front hd10 left noti
|
BLD98-03904
| INSP - Framing/Rough-in | 2/3/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | A | FAIL |
|
|
02/04/99 407 - left corrections.
|
BLD99-00092
| INSP - Foundation | 2/4/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | P | FAIL |
|
|
02/04/99 407 - walls poured prior to 4:00pm inspection .
|
BLD99-00135
| INSP - Foundation | 2/4/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | P | PASS |
|
|
02/04/99 407 - footings ok.
|
BLD98-03630
| INSP - Framing/Rough-in | 2/4/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | P | PART |
|
|
02/04/99 407 - has some corrections.
|
MEC98-04101
| INSP - Final | 2/4/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | P | NH |
|
|
02/04/99 407 - ###-#### Lars
|
MEC98-04101
| INSP - Final | 2/4/1999 | 2/4/1999 | 2/4/1999 12:00:00 AM | P | NH |
|
|
02/04/99 407 - ###-#### Lars
|
BLD98-03826
| INSP - Final | 2/3/1999 | 2/4/1999 | 2/3/1999 12:00:00 AM | A | NR |
|
|
02/04/99 407 - need other items addressed,shell and core.
|
BLD98-02386
| INSP - Final | 2/4/1999 | 2/4/1999 | 2/3/1999 12:00:00 AM | P | PASS |
|
|
02/04/99 407 - U.S. Bank @ M.K.
|