Inspections for the day of: Friday, February 4, 2000.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-03639 BLD-Other2/3/20002/4/20002/4/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 02/03/2000 at 09:20:49. Contact: ###-####. Met w/ eng'r & spec insp onsite (MTI) Agreement letter forthcoming. WIP ok
BLD00-00033 BLD-Framing/Rough-in2/3/20002/4/20002/4/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 02/03/2000 at 12:56:07. Contact: ###-####. Ok to cover partitions. Need clarification of ADA upgrades. $2600 worth per Dan S.
BLD99-02317 BLD-Framing/Rough-in2/3/20002/4/20002/4/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 02/03/2000 at 14:57:11. Contact: ###-####. HP #27 need eng'r approval letter ok to cover elec room only
BLD99-03390 BLD-Foundation2/3/20002/4/20002/4/2000 12:00:00 AMAPASS
Cal; ###-####.
MEC00-00006 Final2/4/20002/4/20002/4/2000 12:00:00 AMAPASS
Final ok.
MEC99-04064 Final2/4/20002/4/20002/4/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 02/04/2000 at 08:42:05. Contact: ###-####. No access flooring work recall
BLD99-00329 BLD-Final2/4/20002/4/20002/4/2000 12:00:00 AMPFAIL
1/800/526/7811 sheila --ann taylor store -fn keep c/n failed fire
BLD99-03561 BLD-Other2/4/20002/4/20002/4/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 02/04/2000 at 09:23:49. Contact: . This is a frame inspection c/n int shear etc. ok to insulate.
BLD99-03450 BLD-Framing/Rough-in2/4/20002/4/20002/4/2000 12:00:00 AMPFAIL
jay ###-#### c/n straps ducts fireblock
BLD99-03139 BLD-Conference2/3/20002/4/20002/4/2000 12:00:00 AMPFAIL
Linda Hackstaff- ###-####; Please call prior to inspection. C/n verify headers @ egress windows elec c/n covered w/o inspection (met with relator & Pat Lass)