Inspections for the day of: Monday, February 4, 2002.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD00-03361 BLD-Framing/Rough-in2/1/20022/4/20022/4/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 02/01/2002 at 16:50:02. Contact: .need all eng's, spec insps ok's; cert of value for modifications req'd 2/4/2002 6:11:21 PM
MIS02-00004 BLD-Conference2/4/20022/4/20022/4/2002 12:00:00 AMAPASS
Scheduled by Inspector: 340 On 2/4/2002 11:15:49 AM ...gave report to church 2/4/2002 12:40:23 PM
MIS00-00136 BLD-Conference2/4/20022/4/20022/4/2002 12:00:00 AMPPART
Added by Inspector: 340 On 2/4/2002 6:21:06 PM w/ Hosac: bring plans?docs for insp & c/o
MIS02-00014 BLD-Conference1/25/20022/4/20022/4/2002 12:00:00 AMPPASS
Scheduled by Inspector: 340 On 1/25/2002 2:27:43 PM follow up on locker room...issued 25 day N&O...due by 3-11-02 2/4/2002 4:30:34 PM
BLD99-03148 BLD-Final2/1/20022/4/20022/4/2002 12:00:00 AMPNR
###-####... n/r verify all other finls & fire status re chimney,grease duct. 2/4/2002 2:36:33 PM
BLD01-02425 BLD-Framing/Rough-in2/4/20022/4/20022/4/2002 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 02/04/2002 at 08:24:39. Contact: ###-####...add'l c/n ...complete fireblox, shearwall details. no insul. 2/4/2002 6:08:42 PM
BLD01-03156 BLD-Conference2/4/20022/4/20022/4/2002 12:00:00 AMPPASS
###-####; w/ arch. Billy English & bldr, re-calc occ. load & submit request for use of 36" stairs where > 50 occupants per UBC 1003. 2/4/2002 2:35:29 PM
BLD01-02453 BLD-Framing/Rough-in2/4/20022/4/20022/4/2002 12:00:00 AMPFAIL
###-#### see c/n, need verify elec. 2/4/2002 4:13:56 PM