ESC02-00558
| Site Preparation | 1/30/2003 | 2/4/2003 | 2/4/2003 12:00:00 AM | A | DONE |
|
|
Mud removed from street--wip to other BMP's 2/4/2003 10:42:12 AM
|
ESC02-00571
| Site Final | 1/30/2003 | 2/4/2003 | 2/4/2003 12:00:00 AM | A | DONE |
|
|
Mud removed from street per prior c/n.. Track out provisions in place. Continue to maintain. 2/4/2003 10:41:02 AM 2/4/2003 10:42:45 AM
|
ESC02-00804
| Site Preparation | 2/3/2003 | 2/4/2003 | 2/4/2003 12:00:00 AM | A | DONE |
|
|
|
ESC02-00862
| Site Preparation | 2/4/2003 | 2/4/2003 | 2/4/2003 12:00:00 AM | A | DONE |
|
|
Compliant--Contacted Carl Funk--###-####. Informed him of the compliant. No work observed on site at time of inspection. Minor track out observed. Mr. Funk will address issues and arrange for clean-up. I infomed him that all contractors--Owhyee, United Water and his company need to make arrangements to comply with ESC-8-17. 2/4/2003 9:33:18 AM
|