Inspections for the day of: Wednesday, February 4, 2009.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-01127 FIRE-Final Inspection2/3/20092/4/20092/4/2009 4:02:35 PMPFAIL
The access controlled egress doors are not operational yet. The inspection will be called in for tomorrow.
BLD08-02418 FIRE-Final Inspection2/4/20092/4/20092/4/2009 4:00:41 PMPPASS
life safety passed
FIR08-00772 INSP-Final Inspection2/3/20092/4/20092/4/2009 1:36:44 PMPPART
Permit finaled
FIR08-00772 INSP-Sprinkler Rough-in/Hydro2/3/20092/4/20092/4/2009 1:36:20 PMPPASS
The above ground hydro test passed.
FIR08-00778 INSP-Sprinkler Rough-in/Hydro2/3/20092/4/20092/4/2009 11:01:36 AMADONE
This inspection was actually a conference to see where combustibles above the ceiling had been covered with drywall and areas that had not been covered yet.
FIR08-00367 INSP-Final Inspection2/3/20092/4/20092/4/2009 10:59:59 AMAFAIL
Todays test covered the operation and placement of the audio/visual devices. See the city approved plans for locations where strobes did not work, horns did not work, strobes were blocked by doors or cabinets, strobes were overspaced or the wrong candella. There was an intermittant horn someplace in the warehouse that is not sync'd with the rest of the horns. The supervision of NAC 2 and 3 was also verified with the main FACP.