BLD00-01590
| BLD-Final | 2/2/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | A | FAIL |
|
|
Pete ###-####; c/n, need statement for door hdwe, achd?? ok for t/o. 2/5/2001 12:34:48 PM
|
BLD00-03328
| BLD-Framing/Rough-in | 2/2/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | A | PART |
|
|
t-bar ceiling reinspection ###-#### 2051, per manuf's spec re seismic spacing 2/5/2001 12:00:32 PM
|
BLD00-03328
| BLD-Final | 2/2/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | A | PASS |
|
|
###-#### 2051
|
BLD01-00184
| BLD-Footing | 2/5/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 340 On 2/5/2001 9:41:10 AM ok to pour if thawed & plbg ok, explained slab insul, ok
|
BLD01-00184
| BLD-Footing | 2/5/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | P | PART |
|
|
###-####
|
BLD00-02347
| BLD-Framing/Rough-in | 2/5/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | P | FAIL |
|
|
joe ###-#### shear nail, c/n; coil straps at roof, install hd's as req 2/5/2001 5:10:12 PM d 2/5/2001 5:10:17 PM
|
BLD99-03383
| BLD-Conference | 2/5/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 340 On 2/5/2001 12:04:55 PM w/ proj engr; resub. re boxes
|
BLD01-00241
| BLD-Framing/Rough-in | 2/5/2001 | 2/5/2001 | 2/5/2001 12:00:00 AM | P | PART |
|
|
Don Bryan, ###-####, walls ok, existing clg 2/5/2001 3:42:26 PM
|