Inspections for the day of: Monday, February 5, 2007.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00592 INSP-Final Inspection2/2/20072/5/20072/5/2007 4:38:48 PMPCANC
Could not get access to the project due to an accident.
FIR06-00957 INSP-Sprinkler Rough-in/Hydro2/2/20072/5/20072/5/2007 4:36:40 PMAPASS
First floor of the C wing rough-in piping was completed today. Contractor needs to provide verification from truss manufacturer for the mounting of the eq bracing and the hanging of the 3" main.
FIR05-00479 INSP-Final Inspection2/5/20072/5/20072/5/2007 4:34:24 PMAFAIL
The remaining areas of the first floor were tested by Brian today except for the east elevator. See the city approved plans for locations of deficiencies.
FIR06-00779 INSP-Final Inspection2/2/20072/5/20072/5/2007 12:43:45 PMAPASS
permit finaled
FIR06-00591 INSP-Supply line flush2/2/20072/5/20072/5/2007 12:42:28 PMAPART
Underground flush passed. Overhead rough-in passed except for the 1 1/4" line to be run under the mezzanine. Fire pump has not been installed yet. Plans need to be resubmitted due to additional heads in the east end lower level calc area.