FIR05-00365
| INSP-Final Inspection | 2/4/2008 | 2/5/2008 | 2/5/2008 4:32:41 PM | A | PASS |
|
|
Permit finaled
|
BLD06-02599
| FIRE-Final Inspection | 2/5/2008 | 2/5/2008 | 2/5/2008 4:28:16 PM | P | FAIL |
|
|
Repair the emergency lights as marked on the city approved plans. Provide current inspections for the fire extinguishers in the breakroom and the computer room.
|
FIR08-00009
| INSP-Final Inspection | 2/4/2008 | 2/5/2008 | 2/5/2008 4:00:00 PM | P | FAIL |
|
|
The sprinkler heads are overspaced. Per Jake this will be remedied and called for re-inspection tomorrow.
|
FIR07-00546
| INSP-Sprinkler Rough-in | 2/5/2008 | 2/5/2008 | 2/5/2008 3:58:40 PM | P | PASS |
|
|
As-builts need to be provided showing the additional heads. Several heads need tape and foil removed. Provide aux. drain on west end of system as per plans. Provide the correct backflow or provide resubmittals for friction loss verification. Still need to hydro, forward flush and the other finishing touches.
|
FIR07-00578
| INSP-Sprinkler Rough-in | 1/31/2008 | 2/5/2008 | 2/5/2008 1:52:24 PM | A | PASS |
|
|
See the city approved plans for piping locations approved for cover.
|
BLD07-02990
| FIRE-Final Inspection | 2/4/2008 | 2/5/2008 | 2/5/2008 12:14:52 PM | A | PASS |
|
|
fire life safety passed
|
BLD07-01555
| FIRE-Final Inspection | 2/4/2008 | 2/5/2008 | 2/5/2008 11:38:24 AM | A | PART |
|
|
A temporary occupancy was given with sam rogers permission until the correct door hardware is provided on the northwest exit doors.
|