Inspections for the day of: Thursday, February 5, 2009.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-02282 BLD-Aging Inspection2/5/20092/5/20092/6/2009 8:01:59 AM NR
Work is in progress. Waiting for the fire sprinkler work to be complete.
BLD08-02110 FIRE-Final Inspection2/5/20092/5/20092/5/2009 5:15:10 PMPPASS
Life safety passed.
FIR07-01032 INSP-Sprinkler Rough-in/Hydro2/5/20092/5/20092/5/2009 5:08:26 PMPPASS
The hydro test for the first floor skilled nursing dining room passed.
FIR08-00791 INSP-Sprinkler Rough-in2/5/20092/5/20092/5/2009 3:49:06 PMPPASS
The remaining piping can be covered. I noted one sprinkler pendant at the intermediate stair landing is overspaced from the north wall. Also per the builder insulation will be utilized above the ceiling in front of the public restrooms.
FIR08-00593 INSP-Final Inspection2/4/20092/5/20092/5/2009 3:47:13 PMPPASS
Permit finaled
FIR08-00736 FIR-Aging Inspection2/5/20092/5/20092/5/2009 3:42:31 PM DONE
I left a voice mail for the branch manager requesting project status.
BLD08-01127 FIRE-Final Inspection2/4/20092/5/20092/5/2009 3:19:55 PMAPART
The new addition is ok to occupy.
BLD08-02585 FIRE-Final Inspection2/3/20092/5/20092/5/2009 1:50:27 PMAFAIL
The door hardware has not been installed yet.
BLD08-02584 FIRE-Final Inspection2/3/20092/5/20092/5/2009 1:49:50 PMAFAIL
The door hardware has not been installed yet.
BLD08-02583 FIRE-Final Inspection2/3/20092/5/20092/5/2009 1:49:24 PMAFAIL
The door hardware has not been installed yet.