ESC12-01095
| Random Inspection | 2/5/2013 | 2/5/2013 | 2/7/2013 12:04:35 PM | P | PASS |
|
|
Gregory Phone #: ###-####
|
BLD10-02426
| BLD-Aging Inspection | 2/5/2013 | 2/5/2013 | 2/7/2013 10:16:41 AM | | FAIL |
|
|
|
BLD12-02633
| BLD-Foundation | 2/5/2013 | 2/5/2013 | 2/6/2013 9:38:09 AM | P | PART |
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron,, footings ok
|
BLD12-02957
| BLD-Framing/Rough-in | 2/5/2013 | 2/5/2013 | 2/6/2013 8:38:52 AM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger,, ok to insulate
|
ESC12-00992
| Site Preparation | 2/5/2013 | 2/5/2013 | 2/6/2013 8:30:56 AM | P | PASS |
|
|
|
BLD12-02667
| BLD-Conference | 2/5/2013 | 2/5/2013 | 2/5/2013 2:42:50 PM | P | PASS |
|
|
Zack Phone #: ###-####,, clarified some ADA issues
|
ESC12-01146
| Site Preparation | 2/4/2013 | 2/5/2013 | 2/5/2013 1:10:44 PM | A | PASS |
|
|
|
ESC13-00012
| BMP Violation | 2/4/2013 | 2/5/2013 | 2/5/2013 12:55:24 PM | A | PART |
|
|
cleaned up some,,, correction notice posted to get BMPs in place prior to any more work,, need sign visible from the street,, will check back Feb 8th
|
BLD12-03108
| BLD-Foundation | 2/4/2013 | 2/5/2013 | 2/5/2013 12:20:52 PM | A | PART |
|
|
ben Phone #: ###-####,, ok to pour when ready
|
BLD13-00127
| BLD-Foundation | 2/4/2013 | 2/5/2013 | 2/5/2013 11:51:28 AM | A | PART |
|
|
Phone #: 6951097 >> Inspection requested via mobile web by adam,, stem wall poured
|
BLD12-02313
| BLD-Final | 2/4/2013 | 2/5/2013 | 2/5/2013 11:25:13 AM | A | PART |
|
|
garrett Phone #: ###-####,, final ok on inside of home,, cert of occupancy issued,, will need to get the drainage away from the home per code,, bond is in place for exterior grading, etc.
|
BLD12-02957
| BLD-Framing/Rough-in | 2/4/2013 | 2/5/2013 | 2/5/2013 10:46:57 AM | A | NR |
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD12-02633
| BLD-Footing | 2/4/2013 | 2/5/2013 | 2/5/2013 10:43:45 AM | A | FAIL |
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron// need to have 8 inch depth on footings
|