Inspections for the day of: Friday, February 6, 2009.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-01548 BLD-Conference2/5/20092/6/20092/6/2009 3:30:40 PMPPASS
hawk stone Phone #: ###-#### headroom in upstairs restmoo ok
MIS08-00157 MIS-Aging Inspection2/6/20092/6/20092/6/2009 2:30:25 PM PART
wip
BLD09-00002 BLD-Framing/Rough-in2/5/20092/6/20092/6/2009 2:29:23 PMPPART
karl pence Phone #: ###-#### ok to cover floors and one side wall behind bar
ESC08-00982 Random Inspection2/6/20092/6/20092/6/2009 2:28:17 PMPFAIL
site is a mess dirt on sidewalk and some on road told contractor to clean up site I will reinspect monday at insulation inspection
BLD08-02391 BLD-Energy code compliance2/6/20092/6/20092/6/2009 2:24:19 PMPNR
nate Phone #: ###-####
BLD09-00039 BLD-Framing/Rough-in2/5/20092/6/20092/6/2009 2:23:07 PMAPASS
matt Phone #: ###-####
BLD08-01776 BLD-Conference2/4/20092/6/20092/6/2009 2:22:33 PMAPASS
PHIL KRICHBAUN - NOTE: PW AT CONF ASPEN RM 10:00 2 FL Phone #: ###-####
BLD08-01848 BLD-Framing/Rough-in2/5/20092/6/20092/6/2009 9:01:40 AMAPART
Scheduled by a contractor via Hello! on 2/5/2009 at 3:46:58 PM. Contact: ###-####.ok to cover 1hr fire wall around duct work