BLD12-00045
| FIRE-Final Inspection | 2/6/2012 | 2/6/2012 | 2/6/2012 3:47:40 PM | P | PASS |
|
|
life safety passed
|
FIR12-00014
| INSP-Sprinkler Rough-in | 2/6/2012 | 2/6/2012 | 2/6/2012 3:42:06 PM | P | PASS |
|
|
Permit finaled
|
BLD11-02165
| FIRE-Final Inspection | 2/6/2012 | 2/6/2012 | 2/6/2012 3:20:49 PM | A | FAIL |
|
|
Provide correct installation of the roof mounted duct smoke detector. Include ventilation in the housing as discussed.
|
BLD11-02165
| FIRE-Alarm Testing | 2/6/2012 | 2/6/2012 | 2/6/2012 3:13:42 PM | P | FAIL |
|
|
Provide correct installation of the roof mounted duct smoke detector. Include ventilation in the housing as discussed.
|
FIR11-00641
| INSP-Final Inspection | 2/6/2012 | 2/6/2012 | 2/6/2012 3:12:38 PM | P | PASS |
|
|
Permit finaled
|
FIR11-00543
| INSP-Sprinkler Rough-in | 2/6/2012 | 2/6/2012 | 2/6/2012 3:07:19 PM | P | PASS |
|
|
See the as-builts for locations where additional piping can be covered by hard lids.
|
FIR11-00671
| INSP-Sprinkler Rough-in | 2/3/2012 | 2/6/2012 | 2/6/2012 2:39:25 PM | A | PART |
|
|
Part of the rough-in passed but others failed. There are two area of concern where additional fittings have been added and as requested by the approval notes plans will need to be resubmitted. Upright sprinkler protection is overspaced above the slatted ceiling at the north end of the store. A hydro test is also required.
|
FIR11-00607
| INSP-Sprinkler Rough-in | 2/3/2012 | 2/6/2012 | 2/6/2012 2:35:53 PM | A | PASS |
|
|
Hard lid areas are ok to cover.
|
FIR11-00544
| INSP-Supply line flush | 2/3/2012 | 2/6/2012 | 2/6/2012 11:24:28 AM | A | PASS |
|
|
Underground supply line flush passed. On walking through the project I noted alot of painted sprinkler pendants that will require replacement.
|
FIR11-00215
| INSP-Final Inspection | 2/1/2012 | 2/6/2012 | 2/6/2012 9:49:27 AM | A | PASS |
|
|
Permit finaled. Suppression system functioned correctly.
|
BLD11-02750
| FIRE-Final Inspection | 2/3/2012 | 2/6/2012 | 2/6/2012 9:34:20 AM | A | PASS |
|
|
life safety passed
|
BLD11-02749
| FIRE-Final Inspection | 2/3/2012 | 2/6/2012 | 2/6/2012 9:33:41 AM | A | PASS |
|
|
life safety passed
|
FIR12-00025
| INSP-Final Inspection | 2/2/2012 | 2/6/2012 | 2/6/2012 9:32:38 AM | A | PASS |
|
|
Permit finaled. I found two strobes that were overspaced that were relocated as I waited. Also the sample tubes in one of the three duct smoke detectors had been installed backwards. THis was also corrected as I waited.
|
FIR11-00683
| INSP-Alarm Testing | 2/3/2012 | 2/6/2012 | 2/3/2012 10:35:47 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Tate Inspection cancelled from web by: Clint Tate
|
FIR11-00688
| INSP-Alarm Testing | 2/3/2012 | 2/6/2012 | 2/3/2012 10:35:32 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Tate Inspection cancelled from web by: Clint Tate
|
FIR11-00688
| INSP-Sprinkler Rough-in/Hydro | 2/3/2012 | 2/6/2012 | 2/3/2012 9:28:50 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Tate Inspection cancelled from web by: Clint Tate
|