FIR13-00524
| INSP-Sprinkler Rough-in | 2/6/2014 | 2/6/2014 | 2/6/2014 5:18:05 PM | P | PART |
|
|
Okay for ceiling cover.
|
FIR14-00032
| INSP-Final Inspection | 2/6/2014 | 2/6/2014 | 2/6/2014 4:56:58 PM | P | PART |
|
|
Phase one area sprinkler work passed inspection.
|
FIR13-00608
| INSP-Sprinkler Rough-in | 2/5/2014 | 2/6/2014 | 2/6/2014 4:51:34 PM | P | PART |
|
|
Okay to cover corridor and elevator lobby grid ceilings east side 6th floor.
|
FIR13-00580
| INSP-Sprinkler Rough-in | 2/5/2014 | 2/6/2014 | 2/6/2014 1:01:03 PM | A | PART |
|
|
Overhead fire sprinkler work at endo #1 and procedure rooms as marked on stamped plans approved for cover. Revised drawings to be provided at next inspection for branchline routing changes due to building/system zone separation.
|
BLD13-03435
| FIRE-Final Inspection | 2/5/2014 | 2/6/2014 | 2/6/2014 12:56:43 PM | A | PASS |
|
|
Life safety okay for final pending building address is posted and one EM light at the basement level is repaired.
|
FIR13-00252
| INSP-Final Inspection | 2/5/2014 | 2/6/2014 | 2/5/2014 12:00:00 AM | A | CANC |
|
|
jonathan Phone #: ###-#### // cancelled per Jonothan, will call back to reschedule 2/5/14 leg
|