PLM02-00241
| Plumbing Rough-in | 2/6/2002 | 2/7/2002 | 2/7/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 360 On 2/6/2002 6:05:18 PM
|
PLM02-00167
| Plumbing Rough-in | 2/6/2002 | 2/7/2002 | 2/7/2002 12:00:00 AM | A | FAIL |
|
|
HENRY ###-#### U. P. C. 905.3 horizontally vent need,s to be 6 inches above flood level rim of fixture being served also need additional nail plates 2/7/2002 9:59:36 AM
|
PLM02-00181
| Groundwork | 2/6/2002 | 2/7/2002 | 2/7/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 02/06/2002 at 15:54:52. Contact: water line in to building ok need vent on outlet sid of grease intercepter trunk lines stub in to west side of building with stub up,s ok. 2/7/2002 6:06:08 PM
|
PLM01-03806
| Final | 2/7/2002 | 2/7/2002 | 2/7/2002 12:00:00 AM | P | PASS |
|
|
|
PLM02-00167
| Plumbing Rough-in | 2/7/2002 | 2/7/2002 | 2/7/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM02-00091
| Plumbing Rough-in | 2/7/2002 | 2/7/2002 | 2/7/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 02/07/2002 at 09:52:21. Contact: ###-####. rough in for urinal in existing men bathroom ok to cover 2/7/2002 3:56:38 PM
|
PLM01-02106
| Plumbing Rough-in | 2/7/2002 | 2/7/2002 | 2/7/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 02/07/2002 at 10:03:08. Contact: ###-####. last section,s of D.W.V. water test to room,s ok 2/7/2002 5:49:19 PM
|