BLD02-03095
| FIRE-Final Inspection | 2/6/2003 | 2/7/2003 | 2/7/2003 12:00:00 AM | A | FAIL |
|
|
door hardware still needs replaced to be ADA approved 2/7/2003 3:46:04 PM
|
BLD02-01629
| FIRE-Final Inspection | 2/6/2003 | 2/7/2003 | 2/7/2003 12:00:00 AM | A | PASS |
|
|
fire life safety finaled 2/7/2003 10:00:19 AM
|
BLD02-01350
| FIRE-Final Inspection | 2/7/2003 | 2/7/2003 | 2/7/2003 12:00:00 AM | P | CANC |
|
|
###-####
|
FIR02-00459
| INSP-Sprinkler Rough-in/Hydro | 2/6/2003 | 2/7/2003 | 2/7/2003 12:00:00 AM | P | PART |
|
|
###-#### The underground supply line is OK to cover from the United Water stub-in to the concrete man hole 2/7/2003 2:22:41 PM
|
BLD02-00728
| FIRE-Final Inspection | 2/6/2003 | 2/7/2003 | 2/7/2003 12:00:00 AM | P | FAIL |
|
|
The permit cannot be finaled due to missing ceiling tile and lack of plan review notes and other misc. items listed on the approved plans. Piping is OK to cover in all areas for the first phase 2/7/2003 3:50:02 PM
|