Inspections for the day of: Thursday, February 7, 2008.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00468 INSP-Alarm Testing2/7/20082/7/20082/7/2008 4:51:17 PMACANC
Scheduled by a contractor via Hello! on 2/7/2008 at 6:58:30 AM.
BLD06-03523 FIRE-Final Inspection2/6/20082/7/20082/7/2008 4:51:03 PMACANC
justin Phone #: ###-####
FIR06-00986 INSP-Final Inspection2/6/20082/7/20082/7/2008 4:49:05 PMPFAIL
Missing several items for final at the riser similar to the adjacent building #2. Not ready for final due to missing and defficient items.
FIR06-00985 INSP-Final Inspection2/6/20082/7/20082/7/2008 4:46:30 PMPFAIL
Provide clearance at the riser/floor slab, missing sprinkler coverage at the riser, missing "911" sign at the bell, provide signage at the floor control valves indicating what system is served, missing orfice at the inspectors test, not all items for final reviewed at this time due to number of defficiencies found.
FIR07-00083 INSP-Final Inspection2/6/20082/7/20082/7/2008 4:42:57 PMPPASS
Fire alarm permit work passed inspection, minor field mods are acceptable, signage at the FACP room door to be provided and verified at life safety final, building addressing corrected while on site per account information, permit finaled.
FIR07-00049 INSP-Final Inspection2/6/20082/7/20082/7/2008 4:40:04 PMPPASS
Fire alarm testing completed satisfactory, need to provide signage at the door to the FACP room, building addressing per the account corrected while on site.
FIR07-00662 INSP-Alarm Testing2/6/20082/7/20082/7/2008 3:37:57 PMAPASS
Completed balance of fire alarm testing including initiation devices on the 3rd and 4th floors, dampers at all floors-(non-functional dampers at the west end floors 1-4 repaired while on site), elevator recall, EOL voltage, closure at one door repaired while on site, signals and account checked, and reinspected noted defficiencies from the previous day for compliance. Need to provide building map at the panel including all initiation devices and their locations per review notes and as discussed, fire alarm permit work approved for final.
BLD06-01671 FIRE-Final Inspection2/7/20082/7/20082/7/2008 11:39:40 AMPPASS
Fire life safety finaled.
BLD06-01671 BLD-Aging Inspection2/6/20082/7/20082/7/2008 11:38:27 AMAPASS
Project is okay for final per project activities and previous inspection completed 4/19/07.
BLD07-02967 FIRE-Final Inspection2/6/20082/7/20082/7/2008 11:12:10 AMAPASS
Remainder of the scope of work passed fire life safety inspection.
FIR08-00042 INSP-Final Inspection2/5/20082/7/20082/7/2008 11:11:17 AMAPASS
Fire alarm modifications passed field testing, permit finaled.
FIR08-00046 INSP-Final Inspection2/7/20082/7/20082/7/2008 12:00:00 AMPPASS
Corrections made per last inspection. KR