Inspections for the day of: Wednesday, February 7, 2018.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-04509 BLD-Final2/6/20182/7/20182/9/2018 9:09:43 AMAPASS
Phone #: ###-#### Inspection requested via web by David Dexter
BLD17-03472 BLD-Framing/Rough-in2/6/20182/7/20182/7/2018 4:33:44 PMPPASS
Justin Phone #: ###-####
BLD17-02920 BLD-Wall Bracing2/7/20182/7/20182/7/2018 3:54:04 PMPPASS
Nigel ###-####
BLD17-02415 BLD-Framing/Rough-in2/7/20182/7/20182/7/2018 3:53:44 PMPPASS
Phone #: ###-#### Inspection requested via web by David Scaggs
BLD17-02415 BLD-Energy code compliance2/7/20182/7/20182/7/2018 3:53:22 PMPPASS
Phone #: ###-#### Inspection requested via web by David Scaggs
BLD17-00356 BLD-Framing/Rough-in2/7/20182/7/20182/7/2018 2:53:35 PMPPASS
Chuck Phone #: ###-####
Frame and Energy Pass.
BLD17-00352 BLD-Framing/Rough-in2/7/20182/7/20182/7/2018 2:52:56 PMPPASS
Chuck Phone #: ###-####
Frame and Energy pass
BLD18-00390 BLD-Footing2/6/20182/7/20182/7/2018 2:28:04 PMPPASS
pour at 3 // curtis Phone #: ###-####
BLD18-00045 BLD-Energy code compliance2/6/20182/7/20182/7/2018 11:19:51 AMANR
Josh Phone #: ###-####
Need Mechanical Rough In approval.
BLD17-03316 BLD-Wall Bracing2/6/20182/7/20182/7/2018 10:52:44 AMAPASS
Shear // Joe Phone #: ###-####
BLD17-01277 BLD-Framing/Rough-in2/6/20182/7/20182/7/2018 10:52:05 AMAPASS
Julio Phone #: ###-####
BLD17-01277 BLD-Ceiling Grid Inspection2/6/20182/7/20182/7/2018 10:51:47 AMAPASS
Julio Phone #: ###-####