BLD99-02669
| BLD-Framing/Rough-in | 2/7/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 02/07/2000 at 17:52:16. Contact: ###-####. pending special inspection report rebar ok for first lift 2/8/00 10:51:32 AM
|
BLD99-01934
| BLD-Final | 2/8/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | PASS |
|
|
steve ###-#### L/C ok
|
BLD99-03047
| BLD-Final | 2/8/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 02/08/2000 at 10:39:17. Contact: . C/W
|
BLD99-03090
| BLD-Framing/Rough-in | 2/8/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | PART |
|
|
###-#### Paul conf work in progress
|
BLD99-00883
| BLD-Final | 2/7/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | PASS |
|
|
###-#### Joe L/C ok pass
|
BLD99-02344
| BLD-Final | 2/7/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | PART |
|
|
Ernie ###-#### pend fire sign off
|
BLD99-02211
| BLD-Final | 2/7/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | PASS |
|
|
ernie ###-#### Smoke door test both sides of freight elevator ok.
|
BLD99-03180
| BLD-Final | 2/7/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | PART |
|
|
ernie ###-#### ceiling light wires, fire stop corridor 2 areas, spreader bars at pevimitor(?)
|
BLD99-03678
| BLD-Framing/Rough-in | 2/7/2000 | 2/8/2000 | 2/8/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/07/2000 at 13:29:51. Contact: ###-####. Frame ok putty pad/ rafter frame pevimitor for Gyp attachment.
|