Inspections for the day of: Tuesday, February 8, 2000.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-02669 BLD-Framing/Rough-in2/7/20002/8/20002/8/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 02/07/2000 at 17:52:16. Contact: ###-####. pending special inspection report rebar ok for first lift 2/8/00 10:51:32 AM
BLD99-01934 BLD-Final2/8/20002/8/20002/8/2000 12:00:00 AMPPASS
steve ###-#### L/C ok
BLD99-03047 BLD-Final2/8/20002/8/20002/8/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 02/08/2000 at 10:39:17. Contact: . C/W
BLD99-03090 BLD-Framing/Rough-in2/8/20002/8/20002/8/2000 12:00:00 AMPPART
###-#### Paul conf work in progress
BLD99-00883 BLD-Final2/7/20002/8/20002/8/2000 12:00:00 AMPPASS
###-#### Joe L/C ok pass
BLD99-02344 BLD-Final2/7/20002/8/20002/8/2000 12:00:00 AMPPART
Ernie ###-#### pend fire sign off
BLD99-02211 BLD-Final2/7/20002/8/20002/8/2000 12:00:00 AMPPASS
ernie ###-#### Smoke door test both sides of freight elevator ok.
BLD99-03180 BLD-Final2/7/20002/8/20002/8/2000 12:00:00 AMPPART
ernie ###-#### ceiling light wires, fire stop corridor 2 areas, spreader bars at pevimitor(?)
BLD99-03678 BLD-Framing/Rough-in2/7/20002/8/20002/8/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 02/07/2000 at 13:29:51. Contact: ###-####. Frame ok putty pad/ rafter frame pevimitor for Gyp attachment.