BLD17-03220
| BLD-Aging Inspection | 2/8/2018 | 2/8/2018 | 2/13/2018 3:20:30 PM | | PEND |
|
|
|
BLD17-00446
| BLD-Aging Inspection | 2/8/2018 | 2/8/2018 | 2/13/2018 3:19:55 PM | | PEND |
|
|
|
BLD17-03476
| BLD-Aging Inspection | 2/8/2018 | 2/8/2018 | 2/12/2018 7:53:22 AM | | PEND |
|
|
|
BLD16-02408
| BLD-Final | 2/8/2018 | 2/8/2018 | 2/9/2018 4:56:08 AM | P | PASS |
|
|
Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD17-03710
| BLD-Framing/Rough-in | 2/7/2018 | 2/8/2018 | 2/8/2018 5:08:17 PM | P | PART |
|
|
Grant Phone #: ###-####,, see paint corrections,, ok to insulate
|
BLD17-03898
| BLD-Framing/Rough-in | 2/1/2018 | 2/8/2018 | 2/8/2018 5:02:44 PM | P | PASS |
|
|
Mike Phone #: ###-####,, final ok after electrical pass on final
|
BLD17-04055
| BLD-Wall Bracing | 2/7/2018 | 2/8/2018 | 2/8/2018 4:51:58 PM | A | PART |
|
|
BOBBY Phone #: ###-####,, exterior ok after re nailing painted areas
|
BLD17-03460
| BLD-Energy code compliance | 2/8/2018 | 2/8/2018 | 2/8/2018 4:27:38 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD17-02783
| BLD-Final | 2/8/2018 | 2/8/2018 | 2/8/2018 4:10:01 PM | P | PASS |
|
|
Brad Phone #: ###-####
|
BLD17-02783
| DOC - Permit Finaled | 2/8/2018 | 2/8/2018 | 2/8/2018 4:09:53 PM | P | PASS |
|
|
|
MIS17-00376
| MIS-Aging Inspection | 2/8/2018 | 2/8/2018 | 2/8/2018 3:42:28 PM | | PEND |
|
|
|
BLD17-03786
| BLD-Footing | 2/8/2018 | 2/8/2018 | 2/8/2018 3:34:03 PM | P | PART |
|
|
Jay Phone #: ###-####,, work in progress,, ok
|
BLD13-02364
| BLD-Conference | 2/7/2018 | 2/8/2018 | 2/8/2018 2:52:54 PM | P | PEND |
|
|
status review to close out permit
|
BLD17-03371
| BLD-Framing/Rough-in | 2/7/2018 | 2/8/2018 | 2/8/2018 2:50:00 PM | P | PASS |
|
|
Basement - add (2) 2x8 header and floor beams bearing Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD17-03371
| BLD-Energy code compliance | 2/8/2018 | 2/8/2018 | 2/8/2018 2:49:53 PM | P | PASS |
|
|
Basement - add (2) 2x8 header and floor beams bearing Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD18-00008
| BLD-Footing | 2/8/2018 | 2/8/2018 | 2/8/2018 2:21:00 PM | P | PASS |
|
|
This footing inspection can be done later in the PM today. Alex will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
MIS17-00369
| BLD-Conference | 2/5/2018 | 2/8/2018 | 2/8/2018 1:19:26 PM | A | PEND |
|
|
Issue 5 day N&O to obtain permits and approval for an ADU if property appears to be occupied as such.,, owner called and said he would get the process going for the ADU but is out of town,, also said no one is staying in the garage
|
BLD17-04248
| BLD-Wall Bracing | 2/8/2018 | 2/8/2018 | 2/8/2018 1:15:54 PM | A | PART |
|
|
Please call first. Nate Phone #: ###-#### Inspection requested via web by Nate Mitchell,, firewall,, work in progress,, needs fire blocking between walls at 10' max
|
BLD17-03895
| BLD-Framing/Rough-in | 2/7/2018 | 2/8/2018 | 2/8/2018 11:26:46 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Jaysen Porter,, fixes are happening now,, will need a fix from the truss engineer on the back patio trusses where they were cut,, ok to insulate
|
BLD17-02588
| BLD-Footing | 2/7/2018 | 2/8/2018 | 2/8/2018 11:17:38 AM | A | PART |
|
|
Terri Phone #: ###-####,, roadmix in place
|