BLD01-00095
| BLD-Foundation | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 13:29:49. Contact: ###-####.
|
BLD00-02822
| BLD-Footing | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | FAIL |
|
|
###-#### Discrepancy on plans for footing rebar.....Need stamped letter for clarification from Eng prior to pour. 2/9/2001 9:26:43 AM
|
BLD00-03060
| BLD-Other | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 15:54:11. Contact: ###-####. 2/9/2001 10:33:59 AM Last (lift) Grout pour and (top) bond beam on N, E, and W. walls OK. 2/9/2001 10:36:08 AM
|
BLD00-02246
| BLD-Foundation | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 15:59:34. Contact: ###-####. by a contractor via Hello! on 02/08/2001 at 15:59:34. Contact: ###-####. 2/9/2001 11:48:46 AM Grout pour (N.Wall) OK pend special insp and appr. 2/9/2001 11:50:30 AM
|
BLD00-02660
| BLD-Footing | 2/9/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 02/09/2001 at 07:08:07. Contact: ###-####. Footing for East 1/2 of bldg OK pend special insp and appr. 2/9/2001 2:26:37 PM
|
BLD00-03637
| BLD-Framing/Rough-in | 2/9/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/09/2001 at 08:27:52. Contact: ###-####.
|
BLD00-01199
| BLD-Final | 2/9/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | P | PASS |
|
|
Gary ###-#### C/C issued. 2/9/2001 4:32:07 PM
|
BLD01-00096
| BLD-Footing | 2/9/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | P | PART |
|
|
Warren ###-####
|