MEC01-00386
| Final | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 13:27:33. Contact: ###-####.
|
MEC01-00397
| Pressure Test | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | PART |
|
|
pipe from meter to roof only thing tested 2/9/2001 12:44:01 PM
|
MEC01-00394
| Final | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 14:47:36. Contact: ###-####.
|
MEC01-00202
| Final | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 16:25:29. Contact: ###-####.
|
MEC01-00374
| Pressure Test | 2/8/2001 | 2/9/2001 | 2/9/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 15:47:41. Contact: ###-####.
|