BLD14-03533
| FIRE-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 3:42:33 PM | P | CANC |
|
|
wrong permit called in.
|
FIR14-00933
| INSP-Final Inspection | 2/9/2015 | 2/9/2015 | 2/9/2015 3:24:09 PM | P | FAIL |
|
|
All items tested ok except a tamper switch is sending a trouble signal to central station instead of a supervisory
|
BLD14-01590
| FIRE-Final Inspection | 2/9/2015 | 2/9/2015 | 2/9/2015 3:23:21 PM | P | FAIL |
|
|
Life safety will be ok to pass when the project related fire alarm permit is finaled
|
FIR14-00574
| INSP-Sprinkler Rough-in/Hydro | 2/9/2015 | 2/9/2015 | 2/9/2015 3:22:41 PM | P | PASS |
|
|
Overhead hydro tests passed
|
FIR14-00896
| INSP-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 2:41:11 PM | P | PASS |
|
|
Too close uprights have modified.
|
BLD14-01680
| FIRE-Final Inspection | 2/7/2015 | 2/9/2015 | 2/9/2015 2:35:17 PM | A | CANC |
|
|
Wrong permit scheduled
|
BLD14-02980
| FIRE-Final Inspection | 2/6/2015 | 2/9/2015 | 2/9/2015 2:13:21 PM | A | FAIL |
|
|
Gary is not ready for final yet. He will reschedule.
|
FIR14-00574
| INSP-Final Inspection | 2/9/2015 | 2/9/2015 | 2/9/2015 2:04:50 PM | P | PASS |
|
|
Permit finaled
|
BLD13-01820
| FIRE-Final Inspection | 2/9/2015 | 2/9/2015 | 2/9/2015 12:57:08 PM | P | PASS |
|
|
Life safety passed. Roadway surface has been approved.
|
FIR14-00934
| INSP-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 12:56:17 PM | P | PASS |
|
|
Rough-in passed. Piping can be covered.
|
BLD14-01591
| FIRE-Final Inspection | 2/6/2015 | 2/9/2015 | 2/9/2015 9:32:23 AM | A | PASS |
|
|
life safety passed
|