Inspections for the day of: Tuesday, February 9, 2016.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEvan Jenkins
TitleEROSION CONTROL MANAGER
Phone #794-3958
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00803 Aging Inspection2/9/20162/9/20162/10/2016 11:31:54 AM PASS
Minor work occuring. No ESC issues observed at this time
ESC14-00817 Aging Inspection2/9/20162/9/20162/10/2016 9:46:32 AM PEND
ESC near completion. Re-veg still needs to be re-established
ESC15-00306 General Inspection2/9/20162/9/20162/10/2016 9:01:28 AM PASS
Site is in good shape. One issue occured yesterday 2-9-16 on the Head Gate (Canal) Portion of the project. A turbid discharge had occured when they opened the headgates to ensure they are in proper working order. Olivia (RP) stated via phone they had performed Turbidity measurements. They didn't exceed the 50 NTU's above background, plus they are covered under their 404 Permit. No issues at this time
ESC15-00795 Aging Inspection2/9/20162/9/20162/9/2016 3:50:28 PM CANC
ESC15-00882 General Inspection2/9/20162/9/20162/9/2016 2:44:30 PM PASS
ESC15-00356 Aging Inspection2/9/20162/9/20162/9/2016 11:36:19 AM PEND
re-veg
ESC15-00818 General Inspection2/9/20162/9/20162/9/2016 10:40:58 AM PASS
ESC15-00869 General Inspection2/9/20162/9/20162/9/2016 9:15:45 AM PASS
ESC15-00869 DOC - Permit Finaled2/9/20162/9/20162/9/2016 9:15:35 AMPPASS
Complete
ESC conditions satisfied
ESC14-01052 General Inspection2/9/20162/9/20162/9/2016 9:09:44 AM PEND
Perm Re-veg