Inspections for the day of: Friday, March 1, 2002.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC02-00579 Final2/27/20023/1/20023/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 02/27/2002 at 13:39:10. Contact: ###-####.
MEC02-00587 Rough-in2/27/20023/1/20023/1/2002 12:00:00 AMAPART
DICK ###-#### c/n framing not per installation spec on main fireplace--bedroom f.place ok--correct and call for re-inspection. 3/1/2002 11:20:01 AM
MEC02-00532 Rough-in2/28/20023/1/20023/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 02/28/2002 at 09:44:00. Contact: ###-####.
MEC02-00532 Pressure Test2/28/20023/1/20023/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 02/28/2002 at 09:44:43. Contact: ###-####.
BLD02-00037 BLD-Final2/28/20023/1/20023/1/2002 12:00:00 AMAPASS
###-#### c. of c. #22159 issued 3/1/2002 10:20:00 AM
MEC02-00529 Rough-in2/28/20023/1/20023/1/2002 12:00:00 AMANR
Scheduled by a contractor via Hello! on 02/28/2002 at 12:55:06. Contact: ###-####.
MEC01-03839 Final2/28/20023/1/20023/1/2002 12:00:00 AMAPASS
CAROL ###-#### KEY IN F-DOOR OUT LET
MEC02-00370 Rough-in2/28/20023/1/20023/1/2002 12:00:00 AMAPASS
DOUG ###-####
BLD01-02589 BLD-Final2/28/20023/1/20023/1/2002 12:00:00 AMACANC
Scheduled by Inspector: 408 On 2/28/2002 4:57:36 PM
BLD01-02589 BLD-Final2/28/20023/1/20023/1/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 02/28/2002 at 17:14:39. Contact: ###-####. c/n posted--mechancal final needed, elec. plates on outside wall need sealing, remove plastic from smoke det. 3/1/2002 8:39:07 AM
BLD02-00284 BLD-Foundation3/1/20023/1/20023/1/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 03/01/2002 at 01:23:24. Contact: ###-####. wip--5% ready at time of inspection 3/1/2002 8:57:28 AM
BLD02-00283 BLD-Footing3/1/20023/1/20023/1/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 03/01/2002 at 07:28:53. Contact: . wip--5% ready at time of inspection 3/1/2002 9:09:02 AM
MEC02-00609 Rough-in2/28/20023/1/20023/1/2002 12:00:00 AMAPASS
###-####
MEC02-00609 Pressure Test2/28/20023/1/20023/1/2002 12:00:00 AMAFAIL
BLD02-00258 BLD-Foundation2/28/20023/1/20023/1/2002 12:00:00 AMAPART
###-#### wip--ok except f. vents needed prior to pouring. 3/1/2002 10:56:32 AM
BLD02-00046 BLD-Framing/Rough-in2/28/20023/1/20023/1/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 02/28/2002 at 15:01:30. Contact: ###-####. ok to insulate 3/1/2002 1:59:33 PM
BLD02-00108 BLD-Framing/Rough-in3/1/20023/1/20023/1/2002 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 03/01/2002 at 09:49:49. Contact: ###-####. c/n posted on site--do not cover 3/1/2002 2:20:57 PM
BLD01-03250 BLD-Final3/1/20023/1/20023/1/2002 12:00:00 AMPNR
ed ###-#### Contacted builder and plumbing inspector--plumbing inspector needs to review prior to str. inspector for final. 3/1/2002 1:04:04 PM
BLD01-03134 BLD-Framing/Rough-in3/1/20023/1/20023/1/2002 12:00:00 AMPNR
justin ###-#### need mechanical r.i. 3/1/2002 3:15:31 PM
BLD01-02589 BLD-Final3/1/20023/1/20023/1/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 03/01/2002 at 10:57:57. Contact: ###-####. c. of c. #22160 issued. 3/1/2002 1:01:14 PM
BLD01-03057 BLD-Framing/Rough-in2/28/20023/1/20023/1/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 02/28/2002 at 13:26:55. Contact: ###-####. ok to cover 3/1/2002 3:08:26 PM
BLD02-00041 BLD-Framing/Rough-in2/28/20023/1/20023/1/2002 12:00:00 AMPPART
###-#### c/n-ok to insulate 3/1/2002 1:32:27 PM