ELE16-00717
| ELE-Aging Inspection | 3/1/2019 | 3/1/2019 | 3/5/2019 11:17:09 AM | | DONE |
|
|
Talked to Twin Cities Elec on 3/5/19 about scheduling a final for this address.
|
ELE16-00796
| ELE-Aging Inspection | 3/1/2019 | 3/1/2019 | 3/5/2019 10:53:38 AM | | DONE |
|
|
Spoke with Jason on 3/5/19 at 10:50. He said he would try to get it scheduled for a final.
|
ELE19-00461
| Electrical Rough-In | 2/28/2019 | 3/1/2019 | 3/1/2019 2:25:40 PM | P | PASS |
|
|
Please contact Keith Chetta with any questions
Thank you ; have a lovely day! Phone #: ###-#### Inspection requested via web by JENNY EMEL Ok cover misc lights/switches throughout house.
|
ELE19-00637
| Electrical Rough-In | 3/1/2019 | 3/1/2019 | 3/1/2019 1:58:37 PM | P | PASS |
|
|
Cancelled p/s. Was supposed to be a RI for the basement. Ok cover basement.
|
ELE19-00637
| Permanent Service | 2/28/2019 | 3/1/2019 | 3/1/2019 1:58:19 PM | P | CANC |
|
|
Changed out a 6 space weatherproof panel on the outside by the meter to a bigger panel Phone #: ###-#### Inspection requested via web by David Kubik Should have been a RI for the basement.
|
ELE19-00753
| Conference | 3/1/2019 | 3/1/2019 | 3/1/2019 1:38:47 PM | P | DONE |
|
|
Toli Phone #: ###-#### Discussed new meter main re-feeding 200a sub panel inside. Exterior conduit to be mounted.
|
ELE18-00859
| Final | 3/1/2019 | 3/1/2019 | 3/1/2019 12:20:37 PM | P | PASS |
|
|
Just need to final the meyer cabinet, Dan Cromie is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok final. To close out permit.
|
ELE19-00569
| Conference | 2/28/2019 | 3/1/2019 | 3/1/2019 12:08:34 PM | A | DONE |
|
|
Phone #: ###-#### Inspection requested via web by Clinton Warren Discussed 20a for bath GFI, and dedicated for floor heat.
|
ELE16-03836
| Final | 2/26/2019 | 3/1/2019 | 3/1/2019 12:07:06 PM | P | NR |
|
|
Contact person Jared, please call 20 min. prior arrival ###-#### ; Phone #: ###-####
|
ELE19-00714
| Final | 2/28/2019 | 3/1/2019 | 3/1/2019 12:06:26 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Hidajet Zahic Ok final. Panel labeled/intersystem installed.
|
ELE18-01606
| Electrical Rough-In | 2/28/2019 | 3/1/2019 | 3/1/2019 10:56:35 AM | A | PASS |
|
|
First floor D rough in inspection Phone #: ###-#### Inspection requested via web by Stephanie Huston Ok cover 1st floor walls Bldg. D.
|
ELE16-00647
| Final | 3/1/2019 | 3/1/2019 | 3/1/2019 9:54:02 AM | A | PASS |
|
|
Please call me 30 minutes before you show up on the property. Thanks. Phone #: ###-#### Inspection requested via web by PAUL PINNEY Ok final. GFI needed in down stairs for washer. It is accessible, and within 6' of sink. Contractor was on site and installed GFI.
|
ELE18-04340
| Final | 2/28/2019 | 3/1/2019 | 3/1/2019 9:51:04 AM | A | PASS |
|
|
Please call Bill he would like to talk to you. Phone #: ###-#### Inspection requested via web by Rhonda Yoast Ok final.
|