Inspections for the day of: Tuesday, March 10, 2009.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00215 INSP-Final Inspection3/10/20093/10/20093/10/2009 3:54:01 PMPPASS
premit finaled
FIR05-00705 INSP-Final Inspection3/10/20093/10/20093/10/2009 3:44:58 PMPPASS
permit finaled
BLD08-01275 FIRE-Final Inspection3/10/20093/10/20093/10/2009 2:07:27 PMPFAIL
Mount the fire extinguisher on the lower level as discussed and tag both extinguishers. Provide approved single action hardware on the secondary (west) exit door. Per April in addressing the 6205 address will suffice.
FIR09-00157 INSP-Final Inspection3/9/20093/10/20093/10/2009 1:30:04 PMPPASS
permit finaled
FIR09-00115 INSP-Supply line flush3/9/20093/10/20093/10/2009 12:45:51 PMAPASS
This inspection was not for a flush but actually a cover inspection for the remaining sprinkler piping on the second floor. THe piping is ok to cover. Work is not complete in the mechanical room or in the elevator shaft which is not shown on this seto of sprinkler plans.
FIR06-00108 INSP-Final Inspection3/10/20093/10/20093/10/2009 12:01:19 PMAPASS
Permit finaled
BLD09-00039 FIRE-Final Inspection3/9/20093/10/20093/10/2009 10:51:45 AMAPASS
life safety passed
FIR09-00099 INSP-Final Inspection3/9/20093/10/20093/10/2009 10:51:21 AMAPASS
permit finaled.