ELE10-00486
| Rough-In Permanent Service | 3/10/2010 | 3/10/2010 | 3/10/2010 3:50:56 PM | P | CANC |
|
|
Inspection requested from web by: TOM BICANDI Phone #: ###-#### see conf
|
ELE10-00486
| Conference | 3/10/2010 | 3/10/2010 | 3/10/2010 3:40:33 PM | P | DONE |
|
|
Inspection requested from web by: TOM BICANDI Phone #: ###-#### called, talked about service, and areas job needs refined, plenums, boxes, etc, no esc this project
|
ELE10-00074
| Final | 3/10/2010 | 3/10/2010 | 3/10/2010 3:27:40 PM | P | CANC |
|
|
mike Phone #: ###-#### wrong type request, see ri
|
ELE10-00074
| Electrical Rough-In | 3/10/2010 | 3/10/2010 | 3/10/2010 3:27:05 PM | P | PART |
|
|
mike Phone #: ###-#### 2 rooms only ok to cover, no esc this project
|
ELE10-00487
| Electrical Rough-In | 3/10/2010 | 3/10/2010 | 3/10/2010 3:25:23 PM | P | NR |
|
|
Rocky Phone #: ###-#### called, left message, fee due
|
ELE09-02353
| Final | 3/10/2010 | 3/10/2010 | 3/10/2010 2:46:10 PM | P | PASS |
|
|
Tim Phone #: ###-#### ok to final, no esc this project
|
ELE10-00469
| Final | 3/10/2010 | 3/10/2010 | 3/10/2010 2:19:05 PM | P | CANC |
|
|
Please give us as much time as you can with a late inspection today thank you Inspection requested from web by: Brad Baker Phone #: ###-#### see t/s
|
ELE10-00469
| Temporary Service | 3/10/2010 | 3/10/2010 | 3/10/2010 2:18:22 PM | P | PASS |
|
|
Please give us as much time as you can with a late inspection today thank you Inspection requested from web by: Brad Baker Phone #: ###-#### t/s o/h n ok, no esc this project
|
ELE10-00444
| Rough-In Permanent Service | 3/9/2010 | 3/10/2010 | 3/10/2010 1:47:32 PM | P | CANC |
|
|
Any questions please call Terry at ###-####, thx! Inspection requested from web by: Stephen Kren Phone #: ###-#### see ri, hold on service- can't have 2 services on one structure per NEC 230.2
|
ELE10-00444
| Permanent Service | 3/10/2010 | 3/10/2010 | 3/10/2010 1:45:56 PM | P | FAIL |
|
|
Any questions please call Terry at ###-####, thx! Inspection requested from web by: Stephen Kren Phone #: ###-#### NEC 230.2, only one service per structure allowed
|
ELE10-00444
| Electrical Rough-In | 3/10/2010 | 3/10/2010 | 3/10/2010 1:31:14 PM | P | PASS |
|
|
Any questions please call Terry at ###-####, thx! Inspection requested from web by: Stephen Kren Phone #: ###-#### ric ok
|
ELE08-01260
| Final | 3/9/2010 | 3/10/2010 | 3/10/2010 10:54:15 AM | A | NH |
|
|
cyrus if possible around 10ish Phone #: ###-#### called, left notice, fee due
|
ELE10-00405
| Electrical Rough-In | 3/9/2010 | 3/10/2010 | 3/10/2010 9:48:32 AM | A | PASS |
|
|
Key under mat Inspection requested from web by: Dan Rohl Phone #: ###-#### corrections made, ric ok, no esc this project
|
ELE10-00470
| Electrical Rough-In | 3/9/2010 | 3/10/2010 | 3/10/2010 9:24:27 AM | A | PASS |
|
|
Thank you! Inspection requested from web by: Adam Staigle Phone #: ###-#### called, ric ok
|
ELE10-00477
| Conference | 3/9/2010 | 3/10/2010 | 3/10/2010 8:45:47 AM | A | DONE |
|
|
Contact Doug at ###-#### to let you into building. He will be on job site. Inspection requested from web by: Barbara Szurgot Phone #: ###-#### talked about plenum wiring, no esc this project
|
ELE10-00473
| Temporary Service | 3/9/2010 | 3/10/2010 | 3/10/2010 8:02:01 AM | A | PASS |
|
|
Inspection requested from web by: Zane Robertson Phone #: ###-#### called, t/s u/g n ok, no esc this project
|