BLD10-00286
| FIRE-Conference | 3/10/2010 | 3/10/2010 | 3/12/2010 7:09:58 AM | P | DONE |
|
|
Ref. IFC 2006 sec. 906.1 regarding existing class II hose stations at the third floor remodel area.
|
MIS10-00013
| FIR-Final | 3/10/2010 | 3/10/2010 | 3/12/2010 7:03:21 AM | P | PASS |
|
|
Field verified all items on the previous issued correction notice have been finished, fire life safety passed.
|
BLD07-01318
| FIRE-Conference | 3/10/2010 | 3/10/2010 | 3/12/2010 6:56:27 AM | P | DONE |
|
|
On site walkthrough confirmed work appears finished, contractor to request inspections for permit final as required.
|
BLD09-01091
| FIRE-Final Inspection | 3/8/2010 | 3/10/2010 | 3/12/2010 6:53:13 AM | A | PASS |
|
|
Corrections completed, fire life safety final inspection passed. Ceiling at room 319 to remain OTS pending future modifications to be submitted at a later date per contractor.
|
FIR09-00501
| INSP-Final Inspection | 3/10/2010 | 3/10/2010 | 3/12/2010 6:47:41 AM | P | PASS |
|
|
Previous C/N items field verified for completion, fire sprinkler permit finaled.
|
FIR02-00142
| FIR-Aging Inspection | 3/10/2010 | 3/10/2010 | 3/10/2010 12:00:00 AM | | FAIL |
|
|
This is a State owned building and should have been expired.
|