ESC09-00812
| BMP Violation | 3/9/2010 | 3/10/2010 | 3/10/2010 2:16:00 PM | A | PART |
|
|
Water discharge from Quinn's Pond into Pond Number 2 appears to be in compliance. Informed RP that liner repairs are still needed.
|
ESC10-00087
| Site Preparation | 3/10/2010 | 3/10/2010 | 3/10/2010 7:30:46 AM | | CANC |
|
|
Already received inspection
|
ESC10-00010
| Complaint Inspection | 3/10/2010 | 3/10/2010 | 3/10/2010 12:00:00 AM | P | PART |
|
|
Received call from ACHD, Inspector 460 visited site and provide a report to ESC Inspector 420. Called applicant, consultent and Eng. Reminder all parties of the conditions of the permit. Discharges not to exceed pre-development flows into Wallings Creek. Informed parties to manage de-watering according to local and Federal regulations. Inspection will occur on Thursday 3-11 afternoon and if problems persist then a stop work on de-watering will be issued.
|