ELE13-01474
| ELE-Aging Inspection | 3/10/2016 | 3/10/2016 | 3/10/2016 3:57:30 PM | | PASS |
|
|
Waiting on contractor
|
ELE16-00777
| Temporary Service | 3/10/2016 | 3/10/2016 | 3/10/2016 3:54:05 PM | P | PASS |
|
|
Any questions please let me know, thx, TW. Phone #: ###-#### Inspection requested via web by Stephen Kren t/s u/g n ok
|
ELE15-04012
| Electrical Rough-In | 3/10/2016 | 3/10/2016 | 3/10/2016 3:33:57 PM | P | PASS |
|
|
UNDERSLAB Phone #: ###-#### Inspection requested via web by Lori Stout Underslab in MCC room, branch circuit conduits will be just under slab. MCC room slab rough in ok cover
|
ELE16-00727
| Permanent Service | 3/10/2016 | 3/10/2016 | 3/10/2016 3:16:07 PM | P | CANC |
|
|
Please call Shawn 30 min in advance for access. If possible need inspection at 2:30 in order for Idaho Power to reconnect. Thank you. Phone #: ###-#### Inspection requested via web by Kerri Hamilton Called contractor, he asked to reschedule for next day.
|
ELE16-00728
| Final | 3/7/2016 | 3/10/2016 | 3/10/2016 2:45:34 PM | P | FAIL |
|
|
Alteration: Wiring of temporary shed. (6) can lights. Misc. receps. (all GFI protected except for the A/C recep. Note: the owner said he checked and I did not need to pull a permit because it was all temporary. (despite my objections). I was not trying to get away with one. Phone #: ###-#### Inspection requested via web by Craig Korell 400.4- Range cord not listed for subject to physical damage. hard useage or mobile home cord required. Called contractor.
|
ELE15-03396
| Electrical Rough-In | 3/9/2016 | 3/10/2016 | 3/10/2016 1:52:34 PM | P | PASS |
|
|
Mike Phone #: ###-#### S.E. showroom and offices wall rough in ok cover
|
ELE16-00483
| Electrical Rough-In | 3/10/2016 | 3/10/2016 | 3/10/2016 1:01:46 PM | P | PASS |
|
|
Mucho Phone #: ###-#### Hot tub rough in ok
|
ELE15-02908
| Electrical Rough-In | 3/9/2016 | 3/10/2016 | 3/10/2016 11:30:50 AM | A | PASS |
|
|
We are requesting a temporary occupancy inspection for tomorrow in the AM for this project. Our contact is Rod @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate Interior of main sales office tested out so office furnishings can be moved in. Ok install main offices
|
ELE16-00353
| Final | 3/9/2016 | 3/10/2016 | 3/10/2016 10:45:13 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Receptacle outelt removed and blanked. Final ok
|
ESC15-00157
| General Inspection | 3/10/2016 | 3/10/2016 | 3/10/2016 10:40:46 AM | P | PASS |
|
|
Job wrapping up rear landscaping in, sod just installed on west side. site clean.
|
ELE15-03117
| Final | 3/9/2016 | 3/10/2016 | 3/10/2016 10:22:00 AM | A | PASS |
|
|
Greg Milburn is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce Value of ELE permit covers total shell and TI. Asked contractor to call and pull permit for TI, assign to TI BLD, and request inspection for TI final. TI and core and shell tested ok. Final ok
|
ELE16-00372
| Final | 3/9/2016 | 3/10/2016 | 3/10/2016 9:28:27 AM | A | PASS |
|
|
final re-inspection Phone #: ###-#### Inspection requested via web by Rowdy Monroe Final ok
|
ESC15-01482
| General Inspection | 3/10/2016 | 3/10/2016 | 3/10/2016 9:16:11 AM | P | PASS |
|
|
Lot not lanscaped yet but all trash removed. Looks clean
|
ELE16-00333
| Final | 3/10/2016 | 3/10/2016 | 3/10/2016 9:02:04 AM | A | PASS |
|
|
CODE 1234 Phone #: ###-#### Inspection requested via web by Bob Glenn Final ok
|
ESC15-01557
| General Inspection | 3/10/2016 | 3/10/2016 | 3/10/2016 9:01:21 AM | P | PASS |
|
|
Site landscaped. Some trash still present but contained.
|
ELE16-00727
| Permanent Service | 3/9/2016 | 3/10/2016 | 3/10/2016 8:55:58 AM | P | CANC |
|
|
Shawn Case Please call 30 minutes for access. 2:30pm would be ideal for Idaho Power to reconnect power. Thank you Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton Inspection cancelled from web by: Kerri Hamilton
|