Inspections for the day of: Friday, March 10, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00705 INSP-Conference3/10/20173/10/20173/10/2017 11:36:54 AMPDONE
I left message for the fitter and stopped at the project site but made no contact except I did speak to the job superintendant. The answer to the question on whether each head under the furnaces had to be separate is "yes". Two or more heads can not be combined on a single drop. Each head needs its owner supply.
FIR16-00647 INSP-Final Inspection3/10/20173/10/20173/10/2017 11:08:23 AMPPASS
Life safety passed
BLD16-03296 FIRE-Final Inspection3/10/20173/10/20173/10/2017 11:07:45 AMPPASS
Life safety passed
FIR16-00811 INSP-Sprinkler Rough-in3/10/20173/10/20173/10/2017 10:25:44 AMPPASS
The supply piping has been lowered. Underground supply piping is ok to cover.
BLD16-04200 FIRE-Final Inspection3/9/20173/10/20173/10/2017 9:51:11 AMAPASS
Life safety passed
BLD16-04199 FIRE-Final Inspection3/9/20173/10/20173/10/2017 9:50:53 AMAPASS
Life safety passed