BLD01-00374
| BLD-Footing | 3/9/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | A | PART |
|
|
Logan ###-####wip--appears ok- 3/12/2001 8:58:04 AM
|
BLD00-03325
| BLD-Framing/Rough-in | 3/11/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/11/2001 at 21:25:55. Contact: ###-####.
|
BLD01-00479
| BLD-Foundation | 3/7/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | A | PASS |
|
|
re-bar Charity ###-####
|
BLD00-02604
| BLD-Framing/Rough-in | 3/9/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | A | PART |
|
|
shear wall --###-#### samatha: C/N posted--7 retrofitted hd needed in place of hd's which are mispositioned--refer to approved plans page S-1 for inspector note and locations.Ok to cover. 3/12/2001 9:56:32 AM
|
BLD01-00471
| BLD-Foundation | 3/12/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | P | PART |
|
|
61-2262wip-appears ok, 3/12/2001 2:23:39 PM
|
MEC01-00238
| Rough-in | 3/12/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 08:49:09. Contact: ###-####.Prior c/n item corrected. 3/12/2001 1:20:05 PM
|
BLD01-00444
| BLD-Footing | 3/12/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 09:59:17. Contact: ###-####.wip-appears ok--setbacks ok 3/12/2001 3:54:41 PM
|
BLD01-00371
| BLD-Footing | 3/12/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | P | PART |
|
|
###-####wip--appears ok 3/12/2001 1:55:46 PM
|
MEC01-00581
| Rough-in | 3/12/2001 | 3/12/2001 | 3/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 11:14:41. Contact: ###-####.
|
BLD00-02604
| BLD-Other | 3/9/2001 | 3/12/2001 | 3/9/2001 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 03/09/2001 at 09:02:59. Contact: ###-####.
|