ESC12-00958
| General Inspection | 3/12/2013 | 3/12/2013 | 3/14/2013 8:33:01 AM | | DONE |
|
|
|
BLD12-03077
| BLD-Final | 3/12/2013 | 3/12/2013 | 3/12/2013 4:56:01 PM | P | NR |
|
|
Raul Phone #: ###-####. No access to inside of home due to hardwood floors being finished.
|
BLD13-00263
| BLD-Footing | 3/11/2013 | 3/12/2013 | 3/12/2013 4:54:41 PM | P | NR |
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. pad still being excavated.
|
ESC13-00031
| General Inspection | 3/12/2013 | 3/12/2013 | 3/12/2013 2:20:56 PM | P | PASS |
|
|
|
BLD13-00069
| BLD-Framing/Rough-in | 3/12/2013 | 3/12/2013 | 3/12/2013 1:36:33 PM | P | FAIL |
|
|
Mike Phone #: ###-####. Provide additional lateral bracing (purlin) on top chord of trusses at north and south overbuilds were roof sheathing has been stopped. ok to insulate.
|
BLD12-00680
| BLD-Footing | 3/11/2013 | 3/12/2013 | 3/12/2013 11:55:26 AM | A | CANC |
|
|
mike Phone #: ###-####. Inspection done yesterday in the pm.
|
GCB12-00162
| GCB-Footing | 3/11/2013 | 3/12/2013 | 3/12/2013 9:18:45 AM | A | PART |
|
|
Mark ###-#### requested by 10AM if possible. Perimeter footing for pump station. Will have special inspection. (strata) Contractor to provide RFI from engineer of record deleting the #5 transverese reinforcement at 16 inches o.c. in the footing as shown on approved plans.
|