Inspections for the day of: Thursday, March 13, 1997.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAlan Hauser
TitleMEC-COM/RES INSPECTOR
Phone #794-9453
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC97-00649 INSP - Rough-in & Gas Pressure3/13/19973/13/19973/13/1997 12:00:00 AM PASS
/ / 350 - r/i ok, pt ok
BLD97-00222 INSP - Framing/Rough-in3/13/19973/13/19973/13/1997 12:00:00 AM PASS
/ / 350 - frame ok, metal let-in-braces in some corners, will nail gyp brace panel. ok to insulate
BLD97-00222 INSP - Framing/Rough-in3/13/19973/13/19973/13/1997 12:00:00 AM PASS
/ / 350 - frame ok, metal let-in-braces in some corners, will nail gyp brace panel. ok to insulate
MEC97-00268 INSP - Final3/12/19973/13/19973/13/1997 12:00:00 AMAPASS
03/13/97 350 - final, couldn't find a card to sign
MEC97-00268 INSP - Final3/12/19973/13/19973/13/1997 12:00:00 AMAPASS
03/13/97 350 - final, couldn't find a card to sign
MEC97-00615 INSP - Rough-in & Gas Pressure3/12/19973/13/19973/13/1997 12:00:00 AMAPASS
03/13/97 350 - r/i ok, pt ok
MEC97-00645 INSP - Rough-in & Gas Pressure3/12/19973/13/19973/13/1997 12:00:00 AMAPASS
03/13/97 350 - r/i ok, pt ok
MEC97-00649 INSP - Rough-in & Gas Pressure3/12/19973/13/19973/13/1997 12:00:00 AMANR
03/13/97 350 - not ready, called for p.m.
BLD95-02164 INSP - Carpentry3/12/19973/13/19973/13/1997 12:00:00 AMAPASS
03/13/97 350 - beam on wall rebar clearances ok, as per plan
BLD96-02429 INSP - Framing/Rough-in3/12/19973/13/19973/13/1997 12:00:00 AMAPASS
03/13/97 350 - frame ok, ok to insulate
BLD96-02657 INSP - Final3/12/19973/13/19973/13/1997 12:00:00 AMAFAIL
03/13/97 350 - no final, corrections posted, (two copies)
BLD96-02692 INSP - Final3/12/19973/13/19973/13/1997 12:00:00 AMAFAIL
03/13/97 350 - key over front door no final, corrections posted (two copies)
BLD97-00013 INSP - Foundation3/13/19973/13/19973/13/1997 12:00:00 AMPPASS
03/13/97 350 - WALL REBAR, top half below garage, as per plan (rebar 12"
MEC97-00582 INSP - Framing/ Rough-in3/13/19973/13/19973/13/1997 12:00:00 AMPPASS
03/13/97 350 - first floor in basement/primary air shaft/ inspection on air shaft bottom in basement, ok to cover shaft bottom
BLD97-00222 INSP - Framing/Rough-in3/13/19973/13/19973/13/1997 12:00:00 AMPNR
03/13/97 350 - still need electrical
MEC97-00650 INSP - Rough-in & Gas Pressure3/13/19973/13/19973/13/1997 12:00:00 AMPPART
03/13/97 350 - pt ok, r/i failed, correction posted (two copies)
MEC97-00652 INSP - Rough-in & Gas Pressure3/13/19973/13/19973/13/1997 12:00:00 AMPPASS
03/13/97 350 - r/i ok, pt ok