BLD00-00059
| BLD-Energy code compliance | 3/10/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | A | PASS |
|
|
ross ###-####
|
BLD99-03656
| BLD-Framing/Rough-in | 3/10/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 03/10/2000 at 14:35:10. Contact: ###-####.
|
BLD99-03555
| BLD-Foundation | 3/9/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | A | FAIL |
|
|
Rejected MTI report, need scope of work letter & log in sheet, compaction report required- DO NOT POUR 3/24/00 1:57:13 PM
|
BLD99-03699
| BLD-Framing/Rough-in | 3/10/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | A | PASS |
|
|
###-#### Shear ok 3/24/00 1:43:58 PM
|
BLD00-00540
| BLD-Framing/Rough-in | 3/10/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | A | PASS |
|
|
craig ###-#### 2nd & 3rd floor wall framing ok 3/24/00 1:57:49 PM
|
BLD00-00316
| BLD-Framing/Rough-in | 3/10/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/10/2000 at 13:22:38. Contact: .
|
BLD00-00316
| BLD-Framing/Rough-in | 3/10/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | PASS |
|
|
###-#### ted call first
|
BLD99-03348
| BLD-Footing | 3/10/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/10/2000 at 13:56:57. Contact: . 85' + 20' @ vesitbule ok. 3/14/00 1:44:44 PM
|
BLD99-03286
| BLD-Final | 3/13/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/13/2000 at 09:26:24. Contact: . C/C #18455 issued. 3/14/00 1:45:52 PM
|
BLD00-00333
| BLD-Framing/Rough-in | 3/13/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | FAIL |
|
|
###-#### shear nailing Still nailing @ 4 pm- not close to being ready. 3/14/00 1:45:42 PM
|
BLD00-00500
| BLD-Footing | 3/13/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | PASS |
|
|
###-#### Ftg. ok- check 8" 2nd story stem wall locations. 3/14/00 1:45:23 PM
|
BLD00-00456
| BLD-Footing | 3/13/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | PASS |
|
|
###-#### Ftg. ok. 3/14/00 1:45:08 PM
|
MEC00-00821
| Rough-in | 3/13/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | FAIL |
|
|
###-#### after 2:30 please Contact # is a fax line could not access. 3/14/00 1:44:21 PM
|
MEC00-00821
| Pressure Test | 3/13/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | FAIL |
|
|
###-#### after 2:30 pleasee Contact # is a fax line. 3/14/00 1:44:31 PM
|
MEC00-00794
| Final | 3/14/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | FAIL |
|
|
PT failed, 4lbs. Installation not complete.
|
BLD99-02462
| BLD-Framing/Rough-in | 3/13/2000 | 3/13/2000 | 3/13/2000 12:00:00 AM | P | PART |
|
|
|