Inspections for the day of: Wednesday, March 13, 2002.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00324 BLD-Final3/12/20023/13/20023/13/2002 12:00:00 AMANR
fn occ doug -343-217 3/13/2002 10:02:17 AM Needs ele. and mech. finals prior to building final. 3/13/2002 10:02:47 AM
BLD02-00447 BLD-Foundation3/12/20023/13/20023/13/2002 12:00:00 AMANR
Scheduled by a contractor via Hello! on 03/12/2002 at 10:00:29. Contact: ###-####. No one on site-no plans 3/13/2002 10:28:12 AM
BLD02-00287 BLD-Footing3/12/20023/13/20023/13/2002 12:00:00 AMAPART
###-#### rich wip--70% completed at time of inspection 3/13/2002 10:18:16 AM
BLD01-03119 BLD-Foundation3/12/20023/13/20023/13/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 03/12/2002 at 17:48:27. Contact: ###-####. wip--Basement, garage still needs inspection. 3/13/2002 10:47:41 AM
BLD02-00339 BLD-Foundation3/13/20023/13/20023/13/2002 12:00:00 AMPDONE
###-#### JAMES Already poured at time of inspection. 3/13/2002 3:16:47 PM
BLD02-00390 BLD-Footing3/13/20023/13/20023/13/2002 12:00:00 AMPPART
###-#### RANDY wip 3/13/2002 2:08:29 PM
BLD02-00412 BLD-Footing3/13/20023/13/20023/13/2002 12:00:00 AMPPART
###-#### RANDY wip 3/13/2002 2:08:17 PM
BLD02-00045 BLD-Framing/Rough-in3/13/20023/13/20023/13/2002 12:00:00 AMPPASS
###-#### Ok to cover 3/13/2002 3:46:43 PM
MEC00-01900 Final3/13/20023/13/20023/13/2002 12:00:00 AMPPASS
fn doug --###-####
MEC02-00733 Rough-in3/13/20023/13/20023/13/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 03/13/2002 at 09:55:21. Contact: ###-####.
BLD02-00454 BLD-Footing3/13/20023/13/20023/13/2002 12:00:00 AMPCANC
###-#### JACK
BLD01-02195 BLD-Final3/13/20023/13/20023/13/2002 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 03/13/2002 at 11:11:26. Contact: ###-####. Prior c/n items not completed.
BLD02-00229 BLD-Foundation3/13/20023/13/20023/13/2002 12:00:00 AMPPART
Scheduled by Inspector: 420 On 3/13/2002 1:55:55 PM wip 3/13/2002 2:18:26 PM
BLD02-00358 BLD-Foundation3/13/20023/13/20023/13/2002 12:00:00 AMPPART
Scheduled by Inspector: 420 On 3/13/2002 1:57:27 PM wip--95% ready at time of inspection 3/13/2002 2:01:22 PM
MEC02-00706 Pressure Test3/11/20023/13/20023/13/2002 12:00:00 AMPPASS
###-#### CARLOS ###-####
MEC02-00706 Final3/11/20023/13/20023/13/2002 12:00:00 AMPNR
Contractor will re-call 3/13/2002 12:49:55 PM