BLD05-02158
| FIRE-Final Inspection | 3/11/2008 | 3/12/2008 | | A | |
|
|
|
FIR07-00710
| INSP-Final Inspection | 3/10/2008 | 3/13/2008 | 3/14/2008 1:18:49 PM | A | PART |
|
|
Completed new fire alarm system testing for the networked panel, interconnection to building one, phase two sprinkler system monitoring, notification appliances for the basement parking garage, and elevator monitoring/recall. Common corridors and apartment units not tested at this time, noted wall mounted horn locations are not in compliance with NFPA 72 2002 7.4.6.1- see also fire code review note #28, elevator fire doors at some floors are not adjusted or missing smoke seals, the main entry door mag locks failed to drop out on alarm condition.
|
BLD07-02748
| FIRE-Final Inspection | 3/13/2008 | 3/13/2008 | 3/13/2008 2:33:51 PM | P | NR |
|
|
Inspection intended to be scheduled for 3/14 per contractor, not ready for final at this time.
|
BLD07-02747
| FIRE-Final Inspection | 3/13/2008 | 3/13/2008 | 3/13/2008 2:30:11 PM | P | NR |
|
|
Missing fire extinguishers at some locations per contractor.
|
BLD06-03307
| FIRE-Final Inspection | 3/11/2008 | 3/13/2008 | 3/13/2008 1:36:27 PM | P | NR |
|
|
jose Phone #: ###-####
|
FIR08-00169
| INSP-Final Inspection | 3/13/2008 | 3/13/2008 | 3/13/2008 1:35:51 PM | P | FAIL |
|
|
Demo work has been completed, however two small restrooms and one electrical closet at the south side of the scope of work are to remain and will still require sprinkler coverage.
|
FIR08-00192
| INSP-Sprinkler Rough-in/Hydro | 3/13/2008 | 3/13/2008 | 3/13/2008 1:32:56 PM | P | FAIL |
|
|
Installation of the new wall has created an unprotected pocket at the west office, also need to remove ceiling tile for rough-in inspection of work at the east office.
|
FIR08-00169
| INSP-Final Inspection | 3/12/2008 | 3/13/2008 | 3/13/2008 12:48:37 PM | A | CANC |
|
|
brandon Phone #: ###-#### Inspection cancelled from web by: Jeff Packham
|
BLD06-00076
| BLD-Final | 3/13/2008 | 3/13/2008 | 3/13/2008 12:13:45 PM | P | FAIL |
|
|
Need to repair ceiling adjacent to the smoke detector at the riser room, missing required lane marking at the fire dept. access road, incomplete address at one apartment unit, the project related fire sprinkler permit work has failed final inspection.
|
FIR07-00235
| INSP-Final Inspection | 3/12/2008 | 3/13/2008 | 3/13/2008 12:07:34 PM | A | FAIL |
|
|
The leak at the riser supply piping has not been repaired, discovered an additional leak at a closet sprinkler head in one apartment unit, travel cap at one ssu in a mechanical closet has not been removed, one defective pendent at a stairway needs replaced, missing escutcheon at one DSW, noted two additional painted heads in need of replacement including a DSW and one pendent at a stairway. Recommend contractor to perform a complete walkthrough of the project prior to scheduling a final inspection. Re-inspection fees will apply to the next field visit for project final.
|
FIR07-00236
| INSP-Final Inspection | 3/12/2008 | 3/13/2008 | 3/13/2008 11:42:10 AM | A | PASS |
|
|
Previous c/n items are complete, two painted heads replaced while on site, fire sprinkler permit finaled.
|
FIR06-00889
| INSP-Final Inspection | 3/12/2008 | 3/13/2008 | 3/13/2008 11:40:44 AM | A | PASS |
|
|
Incorrect device addresses at unit 102 amended while on site, relocated smoke alarms are acceptable, fire alarm work passed field testing, permit finaled.
|
FIR06-00888
| INSP-Final Inspection | 3/12/2008 | 3/13/2008 | 3/13/2008 11:34:07 AM | A | PASS |
|
|
Correction notice items verified for compliance, fire alarm final testing passed, permit finaled.
|
BLD06-00075
| FIRE-Final Inspection | 3/12/2008 | 3/13/2008 | 3/13/2008 11:32:42 AM | A | FAIL |
|
|
Provide fire dept. access lane marking per fire code review notes, noted painted and covered fire sprinkler heads at various locations to be replaced prior to final.
|
BLD07-03089
| FIRE-Final Inspection | 3/13/2008 | 3/13/2008 | 3/13/2008 11:26:52 AM | A | PASS |
|
|
Corrections verified for completion, fire life safety inspection passed.
|
FIR07-00710
| INSP-Supply line flush | 3/10/2008 | 3/13/2008 | 3/13/2008 12:00:00 AM | A | CANC |
|
|
bill Phone #: ###-####
|