Inspections for the day of: Wednesday, March 13, 2013.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKimberly M. Johnson
TitleEROSION CONTROL
Phone #208-794-3958
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC12-00599 General Inspection3/8/20133/13/20133/15/2013 3:04:23 PMADONE
Called Jessie (RP) to ask about status of permit amendment. Jessie indicated it should be complete or close to and will follow up with civil engineer.
ESC13-00125 General Inspection3/13/20133/13/20133/15/2013 2:46:11 PM DONE
Knife river to submit new dewatering plan to the City per conference. New parameters consist of 350 - 700 gpm continuously for 6-10 days.
ESC13-00144 Random Inspection3/13/20133/13/20133/13/2013 4:25:50 PMPPART
Conducted partial inspection of staging area and dewatering. In process of dewatering in ACHD ROW to ditch (not boise jurisdication) Left message for Ryan (RP) to schedule walk through. Ponds for dewatering contaminated water must be lined prior to using them. Need to check calcs for tanks size.
ESC12-00024 General Inspection3/13/20133/13/20133/13/2013 1:48:39 PM PASS
ESC12-00974 Conference3/12/20133/13/20133/13/2013 1:34:59 PMPPART
Meet Jon F (RP) at 1:30. Slope has been terraced and heavily seeded with a dryl and seedmix, ryegrass and clover. (reseeded 3/8/12). Mix included fertilizer. Some areas of slope may need re-terraced because of kids playing on it. RP will monitor. Discussed temporary and permanent stabilization requirements with RP
ESC12-01214 BMP Violation3/12/20133/13/20133/13/2013 12:00:00 AMAPASS
ESC13-00068 BMP Violation3/12/20133/13/20133/13/2013 12:00:00 AMAPART
concrete washout removed and cleaned up. Stil has dirt in gutter to sweep up and housekeeping to clean up. Will re-inspect monday 3/18