Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00116 INSP-Final Inspection3/12/20143/13/20143/13/2014 3:34:15 PMPFAIL
Insufficient water supply pressure to complete an acceptable flushing of the new UG fire supply line. *Note- per contractor, new thrust blocking installed.
FIR13-00713 INSP-Sprinkler Rough-in3/13/20143/13/20143/13/2014 3:28:27 PMANR
Items noted include missing SW heads per plan at the stair enclosures, need intermediate temp heads in the furnace closets, min. distance from ceiling fans at some rooms are not met.
BLD06-02323 FIRE-Final Inspection3/12/20143/13/20143/13/2014 3:22:08 PMAPART
Building 2 unit 403 passed fire life safety inspection.
BLD06-02323 FIRE-Final Inspection3/12/20143/13/20143/13/2014 3:20:25 PMAPART
Building 3 unit 305 passed fire life safety inspection.
BLD14-00258 FIRE-Final Inspection3/12/20143/13/20143/13/2014 12:17:13 PMAPASS
Fire life safety is satisfactory pending current certification at the existing fire extinguisher, door hardware per plan note at the new office partitions.
BLD13-03104 FIRE-Final Inspection3/12/20143/13/20143/13/2014 12:13:44 PMAPASS
Fire life safety inspection passed. PFE at the common corridors are due annual certification.
FIR14-00093 INSP-Final Inspection3/13/20143/13/20143/13/2014 12:12:08 PMAPASS
Scope of work passed fire alarm test and inspection. Permit finaled.
BLD13-03478 FIRE-Final Inspection3/12/20143/13/20143/13/2014 8:59:40 AMAPASS
BLD13-03469 FIRE-Final Inspection3/12/20143/13/20143/13/2014 8:58:35 AMAPASS