FIR13-00193
| INSP-Sprinkler Rough-in | 3/12/2014 | 3/13/2014 | 3/13/2014 3:25:25 PM | P | PASS |
|
|
See the city approved plans for location where piping can be covered with todays date.
|
FIR13-00558
| INSP-Final Inspection | 3/13/2014 | 3/13/2014 | 3/13/2014 3:09:20 PM | P | PASS |
|
|
Permit finaled
|
BLD13-02397
| FIRE-Final Inspection | 3/12/2014 | 3/13/2014 | 3/13/2014 3:09:02 PM | P | PASS |
|
|
Life safety passed. Need to provide ADA hardware on the pocket door.
|
FIR13-00697
| INSP-Sprinkler Rough-in | 3/12/2014 | 3/13/2014 | 3/13/2014 2:13:13 PM | A | PASS |
|
|
The remaining piping in the Patient Area is ok to cover. Rough-in passed for the OR area as far as mains/branchlines/hangers/seismic restraint. Will still need rough-in once the drops are cut.
|
FIR14-00054
| INSP-Sprinkler Rough-in/Hydro | 3/7/2014 | 3/13/2014 | 3/13/2014 2:09:30 PM | A | FAIL |
|
|
No city approved plans on site, if shop drawings match city approved resumittal are required showing the changes. Smoke detectors are too close to grills, candellas on strobes are not set correctly, strobes are overspace even if set correctly. FACP has been relocated. Manual pull station has been relocated. No test form provided. No sigal report provided. No test was performed.
|