MEC18-01030
| Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 4:25:38 PM | P | FAIL |
|
|
Rough-in - Call David Phone #: ###-#### Inspection requested via web by Brandon Sorensen- corrections not made- conference tomorrow AM
|
MEC18-00679
| Final | 3/13/2018 | 3/13/2018 | 3/13/2018 3:50:45 PM | P | PART |
|
|
Inspection requested via web by Floyd Floyd Peek- need plenum rated materials in R/A plenum- pvc abs not rated for plenums- plumbing will address issues
|
MEC18-01056
| Pressure Test | 3/13/2018 | 3/13/2018 | 3/13/2018 3:29:05 PM | P | FAIL |
|
|
Inspection requested via web by Ashley Stegemann- see other note
|
MEC18-01056
| Rough-in | 3/13/2018 | 3/13/2018 | 3/13/2018 3:28:40 PM | P | FAIL |
|
|
Inspection requested via web by Ashley Stegemann- no adult at home- reschedule when adult home- no access
|
MEC17-04922
| Final | 3/6/2018 | 3/13/2018 | 3/13/2018 3:02:39 PM | P | PASS |
|
|
Please call the installer Aaron and he will meet you onsite ###-#### after 1pm Phone #: ###-#### Inspection requested via web by Carolyn Rudd- furnac coil ac co ok- no flue pressure test needed
|
MEC18-00972
| Rough-in | 3/13/2018 | 3/13/2018 | 3/13/2018 2:44:04 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- framing needs completed around b vent 2nd floor and firestop install at ceiling
|
MEC18-00972
| Pressure Test | 3/13/2018 | 3/13/2018 | 3/13/2018 2:43:22 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- 20lb gas pass
|
MEC18-00920
| Rough-in | 3/13/2018 | 3/13/2018 | 3/13/2018 2:43:04 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- R/I ok
|
MEC18-00871
| Final | 3/13/2018 | 3/13/2018 | 3/13/2018 2:16:31 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- revised drawings ommitted 2 offices upstairs- ducting, seal ok- final ok- card signed
|
MEC18-00831
| Final | 3/8/2018 | 3/13/2018 | 3/13/2018 2:03:47 PM | P | PASS |
|
|
PM. Please call when on way. Mary ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- ac coil co ok
|
MEC18-00976
| Pressure Test | 3/13/2018 | 3/13/2018 | 3/13/2018 1:32:09 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- 20lb gas pass
|
MEC18-00341
| Final | 3/13/2018 | 3/13/2018 | 3/13/2018 1:18:30 PM | P | PASS |
|
|
final ok- card signed
|
MEC18-00557
| Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 1:17:32 PM | P | PASS |
|
|
BRAD IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- should have been final
|
MEC18-00557
| Final | 3/13/2018 | 3/13/2018 | 3/13/2018 1:16:48 PM | P | PASS |
|
|
BRAD IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- final ok- card signed
|
MEC18-00874
| Rough-in | 3/13/2018 | 3/13/2018 | 3/13/2018 11:29:45 AM | P | PASS |
|
|
Justin (Lynn John called in the inspeciton) Phone #: ###-####- flex and registers in lobby ok- all areas ok for ceiling tiles- waiting on 3 grills to be installed in hard lid- will look at on final
|
MEC17-05236
| Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 11:10:17 AM | P | PART |
|
|
Rough In for 2nd level. Greg will be your contact. Thank you! Phone #: ###-#### Inspection requested via web by Kim Adams- 2nd floor registers, flex and insulation ok- ok for ceiling tiles 2nd floor only
|
MEC18-01134
| Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 10:33:16 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Randy Hart- insulation shield needs secured and tabs bent over to maintain 1" clearance- need to firecaulk all holes on firespot at ceiling can see daylight thru it
|
MEC18-01133
| Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 10:31:04 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Randy Hart- need approved ACCA report onsite to do inspection
|
MEC18-01133
| Pressure Test | 3/12/2018 | 3/13/2018 | 3/13/2018 10:30:31 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Randy Hart- 20lb gas pass
|
MEC18-00871
| Final | 3/12/2018 | 3/13/2018 | 3/13/2018 8:46:40 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- need approved drawings onsite to do inspection- John checking on this
|
MEC18-01100
| Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 8:23:20 AM | A | FAIL |
|
|
rough in - call david with any questions Phone #: ###-#### Inspection requested via web by Brandon Sorensen- need approved ACCA report onsite to do inspection- need to wrap inert tape thru wall penetration on gas line at meter location
|
MEC18-01100
| Pressure Test | 3/12/2018 | 3/13/2018 | 3/13/2018 8:22:10 AM | A | PASS |
|
|
pressure test - call david with questions Phone #: ###-#### Inspection requested via web by Brandon Sorensen- 20lb gas pass
|
MEC16-04976
| Mec-Aging Inspection | 3/13/2018 | 3/13/2018 | 3/13/2018 8:08:35 AM | | PEND |
|
|
contractor will schedule final per phone call
|
MEC16-04975
| Mec-Aging Inspection | 3/13/2018 | 3/13/2018 | 3/13/2018 8:08:06 AM | | PEND |
|
|
contractor will schedule final per phone call
|
MEC18-00976
| Rough-in | 3/13/2018 | 3/13/2018 | 3/13/2018 7:46:40 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by dannyel chaloupka Inspection cancelled from web by: dannyel chaloupka
|
MEC18-00972
| Pressure Test | 3/12/2018 | 3/13/2018 | 3/13/2018 6:46:31 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by dannyel chaloupka Inspection cancelled from web by: dannyel chaloupka
|
MEC18-00972
| Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 6:46:27 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by dannyel chaloupka Inspection cancelled from web by: dannyel chaloupka
|