PLM03-00221
| Groundwork | 3/13/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 3/13/2003 at 12:34:39 PM. Contact: ###-####. need to change two inch cross to 3x2 cross as required by upc 706.2 where inlet,s enter at the same level ( barrel size need,s to be two size,s larger ) 3/14/2003 12:20:26 PM
|
PLM03-00308
| Groundwork | 3/13/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | A | PART |
|
|
PLEASE DO A PARTIAL GROUNDWORK INSPECTION FOR THE CENTER PART OF THE BUILDING, MID AM FRIDAY 3/14/03. THANKS CHRIS.; Phone #: ###-#### Internet Inspection Request from: RENEE CORNWALL kit area groundwork test ok 3/14/2003 12:34:59 PM
|
PLM03-00658
| Plumbing Rough-in | 3/13/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | A | FAIL |
|
|
###-#### need to change vent,s for combination waste and vent system from two to tthree inch also need to provide upper chamber vent on flammable liquid interceptor 3/14/2003 12:08:35 PM
|
PLM02-02202
| Final | 3/13/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 3/13/2003 at 12:24:41 PM. Contact: ###-####. home owner to pull new permit when financially able to afford to install dishwasher 3/14/2003 2:00:21 PM
|
PLM03-00347
| Final | 3/14/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 3/14/2003 at 7:52:35 AM. Contact: ###-####.
|
PLM03-00664
| Water and/or Sewer | 3/14/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM03-00269
| Final | 3/14/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 3/14/2003 at 10:58:13 AM. Contact: ###-####.
|
PLM03-00652
| Sprinkler (Final) | 3/14/2003 | 3/14/2003 | 3/14/2003 12:00:00 AM | P | PASS |
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|