BLD98-03315
| INSP - Final | 3/15/1999 | 3/15/1999 | 3/17/1999 12:00:00 AM | P | FAIL |
|
|
03/15/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
BLD99-00554
| INSP - Framing/Rough-in | 3/12/1999 | 3/15/1999 | 3/16/1999 12:00:00 AM | A | CANC |
|
|
03/15/99 301 - wes did insp 3/15/99
|
BLD99-00140
| INSP - Foundation | 3/12/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | A | PART |
|
|
03/15/99 301 - footing ok spoke w/ingineer of record he will send calcul
|
MEC99-00800
| INSP - Final | 3/12/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | A | FAIL |
|
|
03/15/99 301 - trans to dix
|
MEC99-00800
| INSP - Final | 3/12/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | A | FAIL |
|
|
03/15/99 301 - trans to dix
|
MEC99-00817
| INSP - Final | 3/12/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | A | PASS |
|
|
03/15/99 301 - FNL -OK FINAL
|
MEC99-00817
| INSP - Final | 3/12/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | A | PASS |
|
|
03/15/99 301 - FNL -OK FINAL
|
BLD98-03053
| INSP - Framing/Rough-in | 3/12/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | P | PART |
|
|
03/15/99 301 - c/n isued ok to start gyp.
|
BLD98-03225
| INSP - Framing/Rough-in | 3/15/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | P | PART |
|
|
03/15/99 301 - DENNIS ###-#### SHEAR NAILING exterior sheer ok
|
BLD99-00267
| INSP - Framing/Rough-in | 3/15/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | P | PASS |
|
|
03/15/99 301 - seperation wall\\###-#### gyp ok
|
BLD98-03762
| INSP - Concrete | 3/15/1999 | 3/15/1999 | 3/15/1999 12:00:00 AM | P | PASS |
|
|
03/15/99 301 - covered with special insp report pending.
|